Energy Projects Near You

Solar, wind and battery projects near Dalry (KA24)

32 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KA24 (North Ayrshire): 2 are waiting for a planning decision, 16 approved but not yet running, 7 operational. The largest live scheme is Flemyland Battery Storage (100 MW battery storage, approved on 6 December 2024, not yet built), 5.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32projects within 10 km
2awaiting a decision
16approved, not running
7operational

Projects within 10 km of KA24

Projects of 1 MW and more (31)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Toftsbattery storagebattery storage19.9approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023North Ayrshire0.2
Wardlaw Wood Windfarmbattery storagebattery storage20approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023North Ayrshire2.8
Wardlaw Wood Solar Farmsolar farmsolar farm20approved, not builtupdated Nov 2024Oct 2024granted Nov 2024Nov 2024North Ayrshire2.8
North West Of Jameston Farmbattery storagebattery storage19.9approved, not builtupdated Sep 2021Oct 2018granted Sep 2021Sep 2021North Ayrshire3.5
Auld Claywind farmwind farm9.2refusedupdated Oct 2015Apr 2015refused Sep 2015Oct 2015North Ayrshire3.7
Millour Hill Community Windfarmwind farmwind farm18operationalupdated Mar 2015Jun 2009granted Dec 2009Mar 2015North Ayrshire4.4
Swinlees Wind Farmwind farmwind farm25.6approved, not builtupdated Feb 2026Nov 2024granted Jul 2025Feb 2026North Ayrshire4.5
Hunterstonbattery storagebattery storage5abandonedupdated Apr 2019Jul 2008granted Mar 2011Apr 2019North Ayrshire4.5
Wardlaw Woodwind farmwind farm18operationalupdated Oct 2009Dec 2002granted Sep 2003Oct 2009North Ayrshire4.8
Millour Hill Community Windfarm (Extension)wind farmwind farm6.4operationalupdated Apr 2017Nov 2013granted Jun 2014Apr 2017North Ayrshire5.0
Benthead Farm Solar Farm & Battery Storagesolar farmsolar farm63approved, not builtupdated Feb 2022Dec 2022granted Aug 2023Feb 2022North Ayrshire5.1
Benthead Farm Solar Farm & Battery Storagebattery storagebattery storage31.1approved, not builtupdated Feb 2022Dec 2022granted Aug 2023Feb 2022North Ayrshire5.1
Flemyland Battery Storagebattery storagebattery storage100approved, not builtupdated Dec 2024Nov 2023granted Dec 2024Dec 2024North Ayrshire5.3
Ardoch Farmbattery storagebattery storage20approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025North Ayrshire5.4
Kilwinning Battery Storagebattery storagebattery storage100approved, not builtupdated Jul 2025May 2024granted May 2025Jul 2025North Ayrshire5.6
Meiklelaught Farmbattery storagebattery storage30approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023North Ayrshire5.7
Site To North East Of, Lochcraigs Farmsolar farmsolar farm5operationalupdated Nov 2016May 2015granted Aug 2015Nov 2016North Ayrshire6.0
Castlehill Solar Farmsolar farmsolar farm5abandonedupdated May 2016Aug 2015granted Oct 2015May 2016North Ayrshire6.2
Blackshaw Community Wind Farmwind farmwind farm21refused on appealupdated Aug 2016Apr 2015refused Nov 2015Aug 2016North Ayrshire6.8
Sorbie Farmwind farmwind farm9under constructionupdated Dec 2021Oct 2013granted Jun 2014Dec 2021North Ayrshire6.9
Sorbie Farm wind clusterwind farmwind farm7.5application withdrawnupdated Jul 2013May 2013—Jul 2013North Ayrshire6.9
Ardeerwind farmwind farm22application withdrawnupdated Aug 2004——Aug 2004North Ayrshire7.3
Kelburnwind farmwind farm28operationalupdated May 2012Jul 2004granted Aug 2009May 2012North Ayrshire7.7
Ardeer Peninsula, Ardeerwind farmwind farm9.6approved, not builtupdated Feb 2026Sep 2023granted Jan 2026Feb 2026North Ayrshire8.6
High Boydstone Farmbattery storagebattery storage100approved, not builtupdated Jul 2025Oct 2024granted Jun 2025Jul 2025North Ayrshire9.0
Standingstone Hillwind turbinewind turbine2.5approved, not built may be out of dateupdated Nov 2019Jan 2019granted Nov 2019Nov 2019North Ayrshire9.0
Ardrossanwind farmwind farm24operationalupdated Aug 2004May 2002granted Jan 2003Aug 2004North Ayrshire9.2
Ardrossan Extensionwind farmwind farm6operationalupdated Jan 2012Dec 2005granted Nov 2007Jan 2012North Ayrshire9.2
Crosbie Wind Farmbattery storagebattery storage50application submittedupdated Apr 2025Jan 2025—Apr 2025North Ayrshire9.3
Crosbie Wind Farmwind farmwind farm98application submittedupdated Apr 2025Jan 2025—Apr 2025North Ayrshire9.3
Wings Lawwind farmwind farm48appeal withdrawnupdated Sep 2014Aug 2007refused Feb 2009Sep 2014North Ayrshire9.8
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Stevenston Sewage Treatment Workssolar farmsolar farm0.6approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025North Ayrshire8.6

Distance from the average position of the KA24 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5031083.6
Wind farm151362142
Wind turbine101002.5
Battery storage111900491

MW in pipeline: pending, approved and under-construction capacity.

How North Ayrshire decides solar, wind and battery applications

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

All projects in North Ayrshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KA24, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.