Hunterston (5 MW battery storage)

Hunterston is a 5 MW battery storage project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 29 April 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWbattery storage
abandonedstatus in REPD
29 April 2019record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
15 July 2008Application submitted
23 March 2011Planning permission granted
23 March 2014Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
29 April 2019
Operator or applicant
Scottish Enterprise/SSE
Planning authority
North Ayrshire
Planning application reference
08/00576/PPP
Address (REPD)
Caledonia Road Lochshore Ind Est, Glengarnock, Beith,
Council area (by location)
North Ayrshire
Time to decision
140 weeks
REPD reference
412

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Swinlees Wind Farmwind farm25.6approved, not built3.4
Toftsbattery storage19.9approved, not built4.4
Wardlaw Wood Windfarmbattery storage20approved, not built5.3
Wardlaw Wood Solar Farmsolar farm20approved, not built5.3
North West Of Jameston Farmbattery storage19.9approved, not built5.8
Millour Hill Community Windfarmwind farm18operational6.4
Wings Lawwind farm48appeal withdrawn6.5
Millour Hill Community Windfarm (Extension)wind farm6.4operational6.6
Benthead Farm Solar Farm & Battery Storagesolar farm63approved, not built6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.743, -4.6759).