Solar, wind and battery projects near Lochwinnoch (PA12)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA12 (Renfrewshire): 7 approved but not yet running. The largest live scheme is Neilston Greener Grid Park - Phase 2 (750 MW battery storage, approved on 13 August 2025, not yet built), 10.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
0awaiting a decision
7approved, not running
0operational

Projects within 10 km of PA12

Projects of 1 MW and more (11)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
West Mitchelton Farm Solar Arraysolar farmsolar farm4.9refused on appealupdated Nov 2016Nov 2015refused Feb 2016Nov 2016Renfrewshire2.6
Weels Farm Solar Arraysolar farmsolar farm4.9refused on appealupdated Jan 2017Nov 2015refused Feb 2016Jan 2017Renfrewshire2.8
Wings Lawwind farmwind farm48appeal withdrawnupdated Sep 2014Aug 2007refused Feb 2009Sep 2014North Ayrshire5.4
Standingstone Hillwind turbinewind turbine2.5approved, not built may be out of dateupdated Nov 2019Jan 2019granted Nov 2019Nov 2019North Ayrshire6.3
Hunterstonbattery storagebattery storage5abandonedupdated Apr 2019Jul 2008granted Mar 2011Apr 2019North Ayrshire6.5
Locher Works, Kilbarchan Roadsolar farmsolar farm3approved, not builtupdated Sep 2024Mar 2024granted Sep 2024Sep 2024Renfrewshire7.0
Swinlees Wind Farmwind farmwind farm25.6approved, not builtupdated Feb 2026Nov 2024granted Jul 2025Feb 2026North Ayrshire8.2
Neilstonbattery storagebattery storage150approved, not builtupdated Sep 2025Dec 2023granted Feb 2025Sep 2025East Renfrewshire8.8
Houston Solar PV Farm & Energy Storage Facilitysolar farmsolar farm75approved, not builtupdated Jun 2026Oct 2023granted Mar 2026Jun 2026Renfrewshire9.5
Houston Solar PV Farm & Energy Storage Facilitybattery storagebattery storage25approved, not builtupdated Jun 2026Oct 2023granted Mar 2026Jun 2026Renfrewshire9.5
Neilston Greener Grid Park - Phase 2battery storagebattery storage750approved, not builtupdated Oct 2025Dec 2024granted Aug 2025Oct 2025Renfrewshire10.0

Distance from the average position of the PA12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4020278
Wind farm2010025.6
Wind turbine101002.5
Battery storage40300925

MW in pipeline: pending, approved and under-construction capacity.

How Renfrewshire decides solar, wind and battery applications

ApplicationsRenfrewshireUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused2 of 1012%
Battery storage refused2 of 516%
Median time from submission to decision21.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in Renfrewshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PA12, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.