Wings Law (48 MW wind farm)
Wings Law is a 48 MW wind farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 19 September 2014.
48 MWwind farm
appeal withdrawnstatus in REPD
19 September 2014record last updated
North Ayrshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 3 August 2007 | Application submitted |
| 23 February 2009 | Refused by the planning authority |
| 14 December 2010 | Appeal withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 48 MW
- Status (REPD)
- appeal withdrawn
- Record last updated
- 19 September 2014
- Operator or applicant
- Wind Hydrogen
- Planning authority
- North Ayrshire
- Planning application reference
- 07/00761/PP
- Appeal reference
- 09/00018/REFUSE
- Turbines
- 24
- Address (REPD)
- Ladyland Moor , Kilbirnie
- Council area (by location)
- North Ayrshire
- Time to decision
- 81 weeks
- REPD reference
- 4626
Who decides
| Applications | North Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 47 | 10,236 |
| Refused | 12 (26%) | 19% |
| Solar refused | 1 of 18 | 12% |
| Onshore wind refused | 10 of 21 | 45% |
| Battery storage refused | 1 of 8 | 16% |
| Median time from submission to decision | 24.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Swinlees Wind Farm | wind farm | 25.6 | approved, not built | 5.6 |
| Hunterston | battery storage | 5 | abandoned | 6.5 |
| Kelburn | wind farm | 28 | operational | 7.5 |
| Waterhead Moor | wind farm | 72.5 | application withdrawn | 7.6 |
| Millour Hill Community Windfarm (Extension) | wind farm | 6.4 | operational | 8.1 |
| Millour Hill Community Windfarm | wind farm | 18 | operational | 8.5 |
| Wardlaw Wood Windfarm | battery storage | 20 | approved, not built | 8.7 |
| Wardlaw Wood Solar Farm | solar farm | 20 | approved, not built | 8.7 |
| Wardlaw Wood | wind farm | 18 | operational | 9.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7979, -4.7119).