Wardlaw Wood Solar Farm (20 MW)

Wardlaw Wood Solar Farm is a 20 MW solar farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 November 2024, not yet built; the record was last updated on 18 November 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtstatus in REPD
18 November 2024record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
4 October 2024Application submitted
7 November 2024Planning permission granted
7 November 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
18 November 2024
Operator or applicant
Community Windpower Limited
Planning authority
North Ayrshire
Planning application reference
24/00773/PP
Site area
76.9 ha
Address (REPD)
East Of Wardlaw Wood Windfarm
Council area (by location)
North Ayrshire
Time to decision
5 weeks
Name in REPD
Wardlaw Wood - Solar Farm
REPD reference
17225

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wardlaw Wood Windfarmbattery storage20approved, not built<0.1
Millour Hill Community Windfarmwind farm18operational1.6
Millour Hill Community Windfarm (Extension)wind farm6.4operational2.2
Wardlaw Woodwind farm18operational2.3
Toftsbattery storage19.9approved, not built3.0
Swinlees Wind Farmwind farm25.6approved, not built3.2
Auld Claywind farm9.2refused4.8
Blackshaw Community Wind Farmwind farm21refused on appeal4.9
Kelburnwind farm28operational5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7232, -4.7532).