Millour Hill Community Windfarm (18 MW)

Millour Hill Community Windfarm is an 18 MW wind farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 May 2012; the record was last updated on 25 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
operationalstatus in REPD
25 March 2015record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
25 June 2009Application submitted
16 December 2009Planning permission granted
1 April 2011Construction started
1 May 2012Operational

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
operational
Record last updated
25 March 2015
Operator or applicant
Community Windpower
Planning authority
North Ayrshire
Planning application reference
09/00424/PPM
Turbines
6
Address (REPD)
Baidland Hill,
Council area (by location)
North Ayrshire
Time to decision
25 weeks
REPD reference
3690

Earlier applications for this site

ApplicationMWSubmittedOutcome
Millour Hill Community Windfarm 06/01007/PP181 November 2006refused 13 January 2009

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Millour Hill Community Windfarm (Extension)wind farm6.4operational0.7
Wardlaw Woodwind farm18operational1.3
Wardlaw Wood Windfarmbattery storage20approved, not built1.6
Wardlaw Wood Solar Farmsolar farm20approved, not built1.6
Kelburnwind farm28operational3.4
Swinlees Wind Farmwind farm25.6approved, not built3.5
Blackshaw Community Wind Farmwind farm21refused on appeal4.3
Toftsbattery storage19.9approved, not built4.6
Crosbie Wind Farmbattery storage50application submitted5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7307, -4.775).