Energy Projects Near You

Millour Hill Community Windfarm (Extension) (6.4 MW)

Millour Hill Community Windfarm (Extension) is a 6.4 MW wind farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 4 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.4 MWwind farm
operationalstatus in REPD
4 April 2017record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
21 November 2013Application submitted
18 June 2014Planning permission granted
15 January 2016Construction started
31 March 2016Operational

Project details

Technology
wind farm
Capacity
6.4 MW
Status (REPD)
operational
Record last updated
4 April 2017
Operator or applicant
Community Windpower
Planning authority
North Ayrshire
Planning application reference
13/00647/PP
Turbines
2
Address (REPD)
Site To North Of Baidland Hill Dalry Ayrshire
Council area (by location)
North Ayrshire
Time to decision
30 weeks
REPD reference
4235

Earlier applications for this site

ApplicationMWSubmittedOutcome
Millour Hill Community Windfarm (Extension) 12/00526/PP620 September 2012refused 5 June 2013

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Millour Hill Community Windfarmwind farm18operational0.7
Wardlaw Woodwind farm18operational1.6
Wardlaw Wood Windfarmbattery storage20approved, not built2.2
Wardlaw Wood Solar Farmsolar farm20approved, not built2.2
Kelburnwind farm28operational2.8
Swinlees Wind Farmwind farm25.6approved, not built3.5
Blackshaw Community Wind Farmwind farm21refused on appeal4.5
Crosbie Wind Farmbattery storage50application submitted4.8
Crosbie Wind Farmwind farm98application submitted4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7358, -4.7809).