Swinlees Wind Farm (25.6 MW)

Swinlees Wind Farm is a 25.6 MW wind farm project in North Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 18 July 2025, not yet built; the record was last updated on 26 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25.6 MWwind farm
approved, not builtstatus in REPD
26 February 2026record last updated
North Ayrshirecouncil area

Planning timeline

DateStage
13 November 2024Application submitted
18 July 2025Planning permission granted
18 July 2028Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
25.6 MW
Status (REPD)
approved, not built
Record last updated
26 February 2026
Operator or applicant
The Farm Energy Partnership
Planning authority
North Ayrshire
Planning application reference
24/00843/PPM
Turbines
6
Turbine height
150 m
Address (REPD)
South Hourat Farm Dalry
Council area (by location)
North Ayrshire
Time to decision
35 weeks
Contracts for Difference
AR7a
REPD reference
15412

Who decides

ApplicationsNorth AyrshireUK
Decided applications (solar, wind, battery)4710,236
Refused12 (26%)19%
Solar refused1 of 1812%
Onshore wind refused10 of 2145%
Battery storage refused1 of 816%
Median time from submission to decision24.9 weeks17.0 weeks
Appeals lodged / allowed4 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wardlaw Wood Solar Farmsolar farm20approved, not built3.2
Wardlaw Wood Windfarmbattery storage20approved, not built3.2
Hunterstonbattery storage5abandoned3.4
Millour Hill Community Windfarmwind farm18operational3.5
Millour Hill Community Windfarm (Extension)wind farm6.4operational3.5
Toftsbattery storage19.9approved, not built4.6
Wardlaw Woodwind farm18operational4.8
Kelburnwind farm28operational4.9
Wings Lawwind farm48appeal withdrawn5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7488, -4.7291).