Neilston Greener Grid Park - Phase 2 (750 MW battery storage)

Neilston Greener Grid Park - Phase 2 is a 750 MW battery storage project in Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 August 2025, not yet built; the record was last updated on 3 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

750 MWbattery storage
approved, not builtstatus in REPD
3 October 2025record last updated
Renfrewshirecouncil area

Planning timeline

DateStage
9 December 2024Application submitted
13 August 2025Section 36 consent granted (Scottish Ministers)
13 August 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
750 MW
Status (REPD)
approved, not built
Record last updated
3 October 2025
Operator or applicant
Statkraft UK LTD
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004988
Address (REPD)
Site 400 metres North West of Sergeantlaw, Gleniffer Road, Paisley
Council area (by location)
Renfrewshire
Time to decision
35 weeks
Name in REPD
Neilston Greener Grid Park - Phase 2
REPD reference
15528

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Neilstonbattery storage150approved, not built1.2
Well Streetbattery storage49.5approved, not built5.1
Neilston Greener Grid Parkbattery storage50under construction5.3
Harelaw Renewable Energy Parkwind farm117refused5.5
Neilston Wind Farmwind farm9.2operational5.6
Middleton Road - Linwood Battery Energy Storage Systembattery storage69abandoned5.6
Middleton Farm Cottage, Middleton Roadsolar farm40approved, not built5.6
Saturland Farm, Salterland Roadbattery storage60.8approved, not built6.2
Parkhouse Roadbattery storage24approved, not built6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8042, -4.4677).