Energy Projects Near You

Well Street (49.5 MW battery storage)

Well Street is a 49.5 MW battery storage project in Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 May 2023, not yet built; the record was last updated on 31 March 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWbattery storage
approved, not builtstatus in REPD
31 March 2023record last updated
Renfrewshirecouncil area

Planning timeline

DateStage
16 February 2023Application submitted
23 May 2023Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.5 MW
Status (REPD)
approved, not built
Record last updated
31 March 2023
Operator or applicant
Larkfleet Group
Planning authority
Renfrewshire
Planning application reference
23/0018/PP
Address (REPD)
Former Gasholder Station At Junction With Underwood Road Well Street
Council area (by location)
Renfrewshire
Time to decision
14 weeks
Name in REPD
Well Street - Battery Storage
REPD reference
11473

Who decides

ApplicationsRenfrewshireUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused2 of 1012%
Battery storage refused2 of 516%
Median time from submission to decision21.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Neilston Greener Grid Parkbattery storage50under construction0.6
Laigh Park Water Treatment Worksbattery storage49.5application submitted1.5
Glasgow Airport Solar Farmsolar farm19.9under construction2.0
Barnwell, Wright Streetbattery storage49.9refused2.6
Middleton Farm Cottage, Middleton Roadsolar farm40approved, not built2.7
Middleton Road - Linwood Battery Energy Storage Systembattery storage69abandoned3.3
East Fulwood Energy Storagebattery storage400application submitted4.0
East Fulwood Greenock Road Solar Farmsolar farm14.3approved, not built4.0
Neilston Greener Grid Park - Phase 2battery storage750approved, not built5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8464, -4.4358).