Glasgow Airport Solar Farm (19.9 MW)

Glasgow Airport Solar Farm is a 19.9 MW solar farm project in Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 28 November 2023; the record was last updated on 29 November 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.9 MWsolar farm
under constructionstatus in REPD
29 November 2023record last updated
Renfrewshirecouncil area

Planning timeline

DateStage
9 November 2022Application submitted
6 April 2023Planning permission granted
28 November 2023Construction started

Project details

Technology
solar farm
Capacity
19.9 MW
Status (REPD)
under construction
Record last updated
29 November 2023
Operator or applicant
AGS Airports Limited
Planning authority
Renfrewshire
Planning application reference
22/0746/PP
Site area
29.9 ha
Address (REPD)
50 Metres East Of Walkinshaw Gardens Barnsford Road Paisley
Council area (by location)
Renfrewshire
Time to decision
21 weeks
REPD reference
10549

The scheme also includes battery storage, recorded separately in REPD (under construction).

Who decides

ApplicationsRenfrewshireUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused2 of 1012%
Battery storage refused2 of 516%
Median time from submission to decision21.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Barnwell, Wright Streetbattery storage49.9refused0.8
Laigh Park Water Treatment Worksbattery storage49.5application submitted0.8
Well Streetbattery storage49.5approved, not built2.0
Neilston Greener Grid Parkbattery storage50under construction2.0
East Fulwood Energy Storagebattery storage400application submitted2.9
East Fulwood Greenock Road Solar Farmsolar farm14.3approved, not built2.9
Middleton Farm Cottage, Middleton Roadsolar farm40approved, not built3.2
Middleton Road - Linwood Battery Energy Storage Systembattery storage69abandoned3.9
Artfield Forest Wind Farmwind farm67.2approved, not built5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8638, -4.4282).