Energy Projects Near You

East Fulwood Greenock Road Solar Farm (14.3 MW)

East Fulwood Greenock Road Solar Farm is a 14.3 MW solar farm project in Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 January 2023, not yet built; the record was last updated on 19 August 2025. REPD also records that the planning permission expired on 24 January 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.3 MWsolar farm
approved, not builtmay be out of datestatus in REPD
19 August 2025record last updated
Renfrewshirecouncil area

REPD also records that the planning permission expired on 24 January 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
18 August 2022Application submitted
24 January 2023Planning permission granted
24 January 2026Permission expired

Project details

Technology
solar farm
Capacity
14.3 MW
Status (REPD)
approved, not built
Record last updated
19 August 2025
Operator or applicant
Springfield Limited / Aggreko
Planning authority
Renfrewshire
Planning application reference
22/0582/PP
Site area
41.0 ha
Address (REPD)
Site Between Nether Southbar And East Fulwood Greenock Road, Inchinnan
Council area (by location)
Renfrewshire
Time to decision
23 weeks
Name in REPD
East Fulwood Greenock Road - Solar Farm
REPD reference
9946

Who decides

ApplicationsRenfrewshireUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused2 of 1012%
Battery storage refused2 of 516%
Median time from submission to decision21.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Fulwood Energy Storagebattery storage400application submitted<0.1
Artfield Forest Wind Farmwind farm67.2approved, not built2.5
Middleton Farm Cottage, Middleton Roadsolar farm40approved, not built2.6
Glasgow Airport Solar Farmsolar farm19.9under construction2.9
Middleton Road - Linwood Battery Energy Storage Systembattery storage69abandoned2.9
Barnwell, Wright Streetbattery storage49.9refused3.4
Laigh Park Water Treatment Worksbattery storage49.5application submitted3.7
Well Streetbattery storage49.5approved, not built4.0
Land off Shilton Lanebattery storage19abandoned4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8771, -4.4683).