Energy Projects Near You

Solar, wind and battery projects near Craigends (PA6)

30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA6 (Renfrewshire): 6 are waiting for a planning decision, 18 approved but not yet running, 1 operational. The largest live scheme is Neilston Greener Grid Park - Phase 2 (750 MW battery storage, approved on 13 August 2025, not yet built), 8.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30projects within 10 km
6awaiting a decision
18approved, not running
1operational

Projects within 10 km of PA6

Projects of 1 MW and more (22)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Houston Solar PV Farm & Energy Storage Facilitysolar farmsolar farm75approved, not builtupdated Jun 2026Oct 2023granted Mar 2026Jun 2026Renfrewshire0.8
Houston Solar PV Farm & Energy Storage Facilitybattery storagebattery storage25approved, not builtupdated Jun 2026Oct 2023granted Mar 2026Jun 2026Renfrewshire0.8
Locher Works, Kilbarchan Roadsolar farmsolar farm3approved, not builtupdated Sep 2024Mar 2024granted Sep 2024Sep 2024Renfrewshire2.7
Middleton Road - Linwood Battery Energy Storage Systembattery storagebattery storage69abandonedupdated May 2025Feb 2023granted May 2024May 2025Renfrewshire3.4
Artfield Forest Wind Farmwind farmwind farm67.2approved, not builtupdated Jul 2022Mar 2021granted Feb 2023Jul 2022Renfrewshire3.5
Middleton Road, Linwoodsolar farmsolar farm1.6approved, not builtupdated Feb 2025Apr 2024granted Jan 2025Feb 2025Renfrewshire3.6
Middleton Farm Cottage, Middleton Roadsolar farmsolar farm40approved, not builtupdated Sep 2025Mar 2025granted Sep 2025Sep 2025Renfrewshire4.0
East Fulwood Greenock Road Solar Farmsolar farmsolar farm14.3approved, not built may be out of dateupdated Aug 2025Aug 2022granted Jan 2023Aug 2025Renfrewshire4.5
East Fulwood Energy Storagebattery storagebattery storage400application submittedupdated Jun 2026Jan 2026—Jun 2026Renfrewshire4.5
Land SW of Shilton Cottagebattery storagebattery storage29.9operationalupdated Jun 2026Apr 2018—Jun 2026Renfrewshire5.3
Land off Shilton Lanebattery storagebattery storage19abandonedupdated Nov 2019Aug 2017—Nov 2019Renfrewshire6.4
Well Streetbattery storagebattery storage49.5approved, not builtupdated Mar 2023Feb 2023granted May 2023Mar 2023Renfrewshire6.7
Glasgow Airport Solar Farmsolar farmsolar farm19.9under constructionupdated Nov 2023Nov 2022granted Apr 2023Nov 2023Renfrewshire6.8
Neilston Greener Grid Parkbattery storagebattery storage50under constructionupdated Mar 2026Jan 2021granted Apr 2022Mar 2026Renfrewshire7.2
Laigh Park Water Treatment Worksbattery storagebattery storage49.5application submittedupdated Oct 2025Sep 2025—Oct 2025Renfrewshire7.3
West Mitchelton Farm Solar Arraysolar farmsolar farm4.9refused on appealupdated Nov 2016Nov 2015refused Feb 2016Nov 2016Renfrewshire7.4
Barnwell, Wright Streetbattery storagebattery storage49.9refusedupdated Aug 2024Feb 2024refused May 2024Aug 2024Renfrewshire7.5
Weels Farm Solar Arraysolar farmsolar farm4.9refused on appealupdated Jan 2017Nov 2015refused Feb 2016Jan 2017Renfrewshire7.8
Neilstonbattery storagebattery storage150approved, not builtupdated Sep 2025Dec 2023granted Feb 2025Sep 2025East Renfrewshire7.9
Neilston Greener Grid Park - Phase 2battery storagebattery storage750approved, not builtupdated Oct 2025Dec 2024granted Aug 2025Oct 2025Renfrewshire8.1
Vale of Leven Wind Farmwind farmwind farm70application submitted may be out of dateupdated Nov 2023Oct 2023—Nov 2023West Dunbartonshire8.4
Vale of Leven Wind Farmbattery storagebattery storage20application submitted may be out of dateupdated Nov 2023Oct 2023—Nov 2023West Dunbartonshire8.4
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Middleton Road, Linwoodbattery storagebattery storage—approved, not builtupdated Feb 2025Apr 2024granted Jan 2025Feb 2025Renfrewshire3.6
Cartside Avenue, Inchinnanrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Oct 2022granted Feb 2023Mar 2023Renfrewshire5.6
Bray Controls UK, Fountain Crescentrooftop solarrooftop solar0.2application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024Renfrewshire5.8
Lightyear Building, Marchburn Drive - Block A - Solar Panelsrooftop solarrooftop solar0.4application submittedupdated Mar 2026Jan 2026—Mar 2026Renfrewshire6.8
Glasgow Airport Solar Farmbattery storagebattery storage—under constructionupdated May 2024Nov 2022granted Apr 2023May 2024Renfrewshire6.8
Cpi Medicines Manufacturing Centre, Netherton Squarerooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jul 2023granted Jan 2024Mar 2024Renfrewshire7.1
Finlaystone House, Estate Greenock Roadsolar farmsolar farm0.1approved, not builtupdated Jul 2024Apr 2024granted May 2024Jul 2024Inverclyde8.7
Old Kilpatrick Service Reservoir, Mount Pleasant Roadsolar farmsolar farm0.4approved, not builtupdated Mar 2023Mar 2023granted Oct 2023Mar 2023West Dunbartonshire9.1

Distance from the average position of the PA6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100802154
Rooftop solar422001
Wind farm21100137
Battery storage1437111,494

MW in pipeline: pending, approved and under-construction capacity.

How Renfrewshire decides solar, wind and battery applications

ApplicationsRenfrewshireUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused2 of 1012%
Battery storage refused2 of 516%
Median time from submission to decision21.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in Renfrewshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PA6, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.