Solar, wind and battery projects near Erskine (PA8)
37 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of PA8 (Renfrewshire): 8 are waiting for a planning decision, 23 approved but not yet running, 1 operational. The largest live scheme is Whitehall Battery Storage (560 MW battery storage, approved on 22 July 2025, not yet built), 5.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of PA8
Projects of 1 MW and more (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Land off Shilton Lanebattery storage | battery storage | 19 | abandonedupdated Nov 2019 | Aug 2017 | — | Nov 2019 | Renfrewshire | 2.0 |
| Vale of Leven Wind Farmwind farm | wind farm | 70 | application submitted may be out of dateupdated Nov 2023 | Oct 2023 | — | Nov 2023 | West Dunbartonshire | 2.6 |
| Vale of Leven Wind Farmbattery storage | battery storage | 20 | application submitted may be out of dateupdated Nov 2023 | Oct 2023 | — | Nov 2023 | West Dunbartonshire | 2.6 |
| East Fulwood Greenock Road Solar Farmsolar farm | solar farm | 14.3 | approved, not built may be out of dateupdated Aug 2025 | Aug 2022 | granted Jan 2023 | Aug 2025 | Renfrewshire | 2.8 |
| East Fulwood Energy Storagebattery storage | battery storage | 400 | application submittedupdated Jun 2026 | Jan 2026 | — | Jun 2026 | Renfrewshire | 2.8 |
| Land SW of Shilton Cottagebattery storage | battery storage | 29.9 | operationalupdated Jun 2026 | Apr 2018 | — | Jun 2026 | Renfrewshire | 3.1 |
| Artfield Forest Wind Farmwind farm | wind farm | 67.2 | approved, not builtupdated Jul 2022 | Mar 2021 | granted Feb 2023 | Jul 2022 | Renfrewshire | 3.3 |
| Braidfield Road, Hardgatebattery storage | battery storage | 100 | application submittedupdated Feb 2025 | Dec 2024 | — | Feb 2025 | West Dunbartonshire | 3.7 |
| Barnwell, Wright Streetbattery storage | battery storage | 49.9 | refusedupdated Aug 2024 | Feb 2024 | refused May 2024 | Aug 2024 | Renfrewshire | 4.3 |
| Glasgow Airport Solar Farmsolar farm | solar farm | 19.9 | under constructionupdated Nov 2023 | Nov 2022 | granted Apr 2023 | Nov 2023 | Renfrewshire | 4.4 |
| Laigh Park Water Treatment Worksbattery storage | battery storage | 49.5 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 | Renfrewshire | 5.2 |
| Middleton Farm Cottage, Middleton Roadsolar farm | solar farm | 40 | approved, not builtupdated Sep 2025 | Mar 2025 | granted Sep 2025 | Sep 2025 | Renfrewshire | 5.3 |
| Middleton Road, Linwoodsolar farm | solar farm | 1.6 | approved, not builtupdated Feb 2025 | Apr 2024 | granted Jan 2025 | Feb 2025 | Renfrewshire | 5.6 |
| Middleton Road - Linwood Battery Energy Storage Systembattery storage | battery storage | 69 | abandonedupdated May 2025 | Feb 2023 | granted May 2024 | May 2025 | Renfrewshire | 5.7 |
| Whitehall Battery Storagebattery storage | battery storage | 560 | approved, not builtupdated Jul 2025 | Nov 2023 | granted Jul 2025 | Jul 2025 | East Dunbartonshire | 5.8 |
| Windyhill Battery Storage Facilitybattery storage | battery storage | 200 | under constructionupdated Jun 2026 | Oct 2021 | granted Jun 2022 | Jun 2026 | East Dunbartonshire | 6.0 |
| Well Streetbattery storage | battery storage | 49.5 | approved, not builtupdated Mar 2023 | Feb 2023 | granted May 2023 | Mar 2023 | Renfrewshire | 6.1 |
| Kilpatrick Hillswind farm | wind farm | 60 | application withdrawnupdated Apr 2008 | — | — | Apr 2008 | West Dunbartonshire | 6.3 |
| Neilston Greener Grid Parkbattery storage | battery storage | 50 | under constructionupdated Mar 2026 | Jan 2021 | granted Apr 2022 | Mar 2026 | Renfrewshire | 6.3 |
| Houston Solar PV Farm & Energy Storage Facilitysolar farm | solar farm | 75 | approved, not builtupdated Jun 2026 | Oct 2023 | granted Mar 2026 | Jun 2026 | Renfrewshire | 7.1 |
| Houston Solar PV Farm & Energy Storage Facilitybattery storage | battery storage | 25 | approved, not builtupdated Jun 2026 | Oct 2023 | granted Mar 2026 | Jun 2026 | Renfrewshire | 7.1 |
| Locher Works, Kilbarchan Roadsolar farm | solar farm | 3 | approved, not builtupdated Sep 2024 | Mar 2024 | granted Sep 2024 | Sep 2024 | Renfrewshire | 9.2 |
| Aggreko, Stirling Roadrooftop solar | rooftop solar | 8.8 | application submitted may be out of dateupdated Sep 2022 | Aug 2022 | — | Sep 2022 | West Dunbartonshire | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Bray Controls UK, Fountain Crescentrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Aug 2024 | Jul 2024 | — | Aug 2024 | Renfrewshire | 1.9 |
| Cartside Avenue, Inchinnanrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Mar 2023 | Oct 2022 | granted Feb 2023 | Mar 2023 | Renfrewshire | 2.4 |
| Old Kilpatrick Service Reservoir, Mount Pleasant Roadsolar farm | solar farm | 0.4 | approved, not builtupdated Mar 2023 | Mar 2023 | granted Oct 2023 | Mar 2023 | West Dunbartonshire | 3.5 |
| Glasgow Airport Solar Farmbattery storage | battery storage | — | under constructionupdated May 2024 | Nov 2022 | granted Apr 2023 | May 2024 | Renfrewshire | 4.4 |
| Lightyear Building, Marchburn Drive - Block A - Solar Panelsrooftop solar | rooftop solar | 0.4 | application submittedupdated Mar 2026 | Jan 2026 | — | Mar 2026 | Renfrewshire | 4.7 |
| Allerdyce Roadrooftop solar | rooftop solar | 0.2 | application withdrawnupdated Jun 2025 | Dec 2023 | — | Jun 2025 | Glasgow City | 5.0 |
| Middleton Road, Linwoodbattery storage | battery storage | — | approved, not builtupdated Feb 2025 | Apr 2024 | granted Jan 2025 | Feb 2025 | Renfrewshire | 5.6 |
| Cpi Medicines Manufacturing Centre, Netherton Squarerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jul 2023 | granted Jan 2024 | Mar 2024 | Renfrewshire | 5.7 |
| Decathlon, Old Govan Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Dec 2023 | granted Mar 2024 | Apr 2024 | Renfrewshire | 5.9 |
| Shipyardrooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Glasgow City | 6.1 |
| Glasgow High School, Crow Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | May 2025 | granted Jul 2025 | Aug 2025 | Glasgow City | 7.9 |
| Fifty Pitches Placerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2023 | Aug 2023 | granted Dec 2023 | Dec 2023 | Glasgow City | 8.2 |
| Shipyard, Govan Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jul 2024 | Mar 2024 | granted Jul 2024 | Jul 2024 | Glasgow City | 9.2 |
| Helen Streetrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2023 | Jul 2023 | granted Oct 2023 | Nov 2023 | Glasgow City | 9.9 |
Distance from the average position of the PA8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 7 | 0 | 0 | 154 |
| Rooftop solar | 12 | 3 | 8 | 0 | 0 | 12.3 |
| Wind farm | 3 | 1 | 1 | 0 | 0 | 137 |
| Battery storage | 15 | 4 | 7 | 1 | 1 | 1,454 |
MW in pipeline: pending, approved and under-construction capacity.
How Renfrewshire decides solar, wind and battery applications
| Applications | Renfrewshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 15 | 10,236 |
| Refused | 4 (27%) | 19% |
| Solar refused | 2 of 10 | 12% |
| Battery storage refused | 2 of 5 | 16% |
| Median time from submission to decision | 21.1 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near PA8, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.