Energy Projects Near You

Middleton Farm Cottage, Middleton Road (40 MW solar farm)

Middleton Farm Cottage, Middleton Road is a 40 MW solar farm project in Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 September 2025, not yet built; the record was last updated on 30 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
30 September 2025record last updated
Renfrewshirecouncil area

Planning timeline

DateStage
31 March 2025Application submitted
3 September 2025Planning permission granted
3 September 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
30 September 2025
Operator or applicant
Bluestone Energy Limited
Planning authority
Renfrewshire
Planning application reference
25/0232/PP
Site area
61.8 ha
Address (REPD)
Middleton Farm Cottage, Middleton Road, Linwood, Paisley
Council area (by location)
Renfrewshire
Time to decision
22 weeks
Name in REPD
Middleton Farm Cottage, Middleton Road - Solar Photovoltaic Array
REPD reference
15760

Who decides

ApplicationsRenfrewshireUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused2 of 1012%
Battery storage refused2 of 516%
Median time from submission to decision21.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Middleton Road - Linwood Battery Energy Storage Systembattery storage69abandoned0.7
East Fulwood Energy Storagebattery storage400application submitted2.6
East Fulwood Greenock Road Solar Farmsolar farm14.3approved, not built2.6
Well Streetbattery storage49.5approved, not built2.7
Glasgow Airport Solar Farmsolar farm19.9under construction3.2
Neilston Greener Grid Parkbattery storage50under construction3.3
Laigh Park Water Treatment Worksbattery storage49.5application submitted3.5
Barnwell, Wright Streetbattery storage49.9refused3.9
Artfield Forest Wind Farmwind farm67.2approved, not built4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8546, -4.4763).