Energy Projects Near You

Neilston Greener Grid Park (50 MW battery storage)

Neilston Greener Grid Park is a 50 MW battery storage project in Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 29 August 2023; the record was last updated on 6 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
under constructionstatus in REPD
6 March 2026record last updated
Renfrewshirecouncil area

Planning timeline

DateStage
21 January 2021Application submitted
5 November 2021Refused by the planning authority
7 February 2022Appeal lodged
28 April 2022Planning permission granted
28 April 2022Appeal allowed
29 August 2023Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
under construction
Record last updated
6 March 2026
Operator or applicant
Statkraft UK LTD
Planning authority
Renfrewshire
Planning application reference
21/0034/PP
Address (REPD)
Site 400 metres North West of Sergeantlaw, Gleniffer Road, Paisley
Council area (by location)
Renfrewshire
Time to decision
66 weeks
Name in REPD
Neilston Greener Grid Park
REPD reference
8830

Who decides

ApplicationsRenfrewshireUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused2 of 1012%
Battery storage refused2 of 516%
Median time from submission to decision21.1 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Well Streetbattery storage49.5approved, not built0.6
Laigh Park Water Treatment Worksbattery storage49.5application submitted1.4
Glasgow Airport Solar Farmsolar farm19.9under construction2.0
Barnwell, Wright Streetbattery storage49.9refused2.5
Middleton Farm Cottage, Middleton Roadsolar farm40approved, not built3.3
Middleton Road - Linwood Battery Energy Storage Systembattery storage69abandoned3.9
East Fulwood Energy Storagebattery storage400application submitted4.4
East Fulwood Greenock Road Solar Farmsolar farm14.3approved, not built4.4
Neilston Greener Grid Park - Phase 2battery storage750approved, not built5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8455, -4.4267).