Energy Projects Near You

Solar, wind and battery projects near Glasgow (G53)

61 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of G53 (Glasgow City): 7 are waiting for a planning decision, 41 approved but not yet running, 3 operational. The largest live scheme is Neilston Greener Grid Park - Phase 2 (750 MW battery storage, approved on 13 August 2025, not yet built), 7.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

61projects within 10 km
7awaiting a decision
41approved, not running
3operational

Projects within 10 km of G53

Projects of 1 MW and more (31)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kennishead Roadbattery storagebattery storage40application withdrawnupdated Mar 2026Jun 2025—Mar 2026Glasgow City1.6
Saturland Farm, Salterland Roadbattery storagebattery storage60.8approved, not builtupdated Apr 2025Nov 2023granted Dec 2024Apr 2025Glasgow City1.8
Parkhouse Roadbattery storagebattery storage24approved, not builtupdated Aug 2025Mar 2024granted Aug 2025Aug 2025Glasgow City2.1
Govan Battery Energy Storage Systembattery storagebattery storage49.9application submittedupdated Mar 2025Feb 2025—Mar 2025Glasgow City4.0
Broomloan Roadbattery storagebattery storage49.9approved, not builtupdated Oct 2024Mar 2024granted Oct 2024Oct 2024Glasgow City4.5
Middleton Wind Farmwind farmwind farm12operationalupdated Mar 2015Feb 2008granted Aug 2011Mar 2015East Renfrewshire5.1
Neilston Greener Grid Parkbattery storagebattery storage50under constructionupdated Mar 2026Jan 2021granted Apr 2022Mar 2026Renfrewshire5.4
Laigh Park Water Treatment Worksbattery storagebattery storage49.5application submittedupdated Oct 2025Sep 2025—Oct 2025Renfrewshire5.9
Well Streetbattery storagebattery storage49.5approved, not builtupdated Mar 2023Feb 2023granted May 2023Mar 2023Renfrewshire5.9
Loganswell Farmwind farmwind farm16application withdrawnupdated Sep 2014Apr 2014—Sep 2014East Renfrewshire6.4
Barnwell, Wright Streetbattery storagebattery storage49.9refusedupdated Aug 2024Feb 2024refused May 2024Aug 2024Renfrewshire6.5
Glasgow Airport Solar Farmsolar farmsolar farm19.9under constructionupdated Nov 2023Nov 2022granted Apr 2023Nov 2023Renfrewshire6.7
Neilston Greener Grid Park - Phase 2battery storagebattery storage750approved, not builtupdated Oct 2025Dec 2024granted Aug 2025Oct 2025Renfrewshire7.4
Moorhouse (Eaglesham)wind farmwind farm47.5refused on appealupdated Jan 2013Apr 2010refused Apr 2012Jan 2013East Renfrewshire8.1
Middleton Farm Cottage, Middleton Roadsolar farmsolar farm40approved, not builtupdated Sep 2025Mar 2025granted Sep 2025Sep 2025Renfrewshire8.6
Neilstonbattery storagebattery storage150approved, not builtupdated Sep 2025Dec 2023granted Feb 2025Sep 2025East Renfrewshire8.6
Bonnyton, Kirkton Moor Roadsolar farmsolar farm28approved, not builtupdated Apr 2026Jul 2025granted Feb 2026Apr 2026East Renfrewshire8.6
Whitehill Energy Storagebattery storagebattery storage200approved, not builtupdated Dec 2024Oct 2022granted Oct 2024Dec 2024Glasgow City8.6
Seath Road, Rutherglenbattery storagebattery storage50refusedupdated Apr 2024Sep 2023refused Mar 2024Apr 2024South Lanarkshire8.6
Moorshield Wind Farmwind farmwind farm15approved, not builtupdated Feb 2026Sep 2023granted Sep 2024Feb 2026East Renfrewshire8.8
Cathkin Braes Wind Farm (Castlemilk)wind turbinewind turbine3operationalupdated Sep 2013Sep 2012granted Jan 2013Sep 2013South Lanarkshire9.0
Middleton Road, Linwoodsolar farmsolar farm1.6approved, not builtupdated Feb 2025Apr 2024granted Jan 2025Feb 2025Renfrewshire9.0
Glasgow Road, Eagleshambattery storagebattery storage40approved, not builtupdated May 2025Jan 2025granted Apr 2025May 2025East Renfrewshire9.0
Harelaw Renewable Energy Parkwind farmwind farm117refusedupdated Feb 2014May 2009refused Sep 2013Feb 2014East Renfrewshire9.1
Downiebrae Road, Rutherglenbattery storagebattery storage150approved, not builtupdated Oct 2025Jan 2025granted Sep 2025Oct 2025Glasgow City9.1
Middleton Road - Linwood Battery Energy Storage Systembattery storagebattery storage69abandonedupdated May 2025Feb 2023granted May 2024May 2025Renfrewshire9.2
Dalmarnock Roadbattery storagebattery storage40approved, not built may be out of dateupdated Mar 2021Sep 2021granted Feb 2022Mar 2021South Lanarkshire9.2
East Fulwood Energy Storagebattery storagebattery storage400application submittedupdated Jun 2026Jan 2026—Jun 2026Renfrewshire9.6
East Fulwood Greenock Road Solar Farmsolar farmsolar farm14.3approved, not built may be out of dateupdated Aug 2025Aug 2022granted Jan 2023Aug 2025Renfrewshire9.6
Castlemilk and Carmunnock Community Windpark Trustwind turbinewind turbine2.5refusedupdated Mar 2015Aug 2013refused Nov 2013Mar 2015South Lanarkshire9.7
Neilston Additional Wind Turbinewind turbinewind turbine2.5permission expiredupdated Jul 2020Mar 2014granted Nov 2015Jul 2020East Renfrewshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (30)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Glasgow Museums Resource Centre, Woodhead Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Nov 2024granted Feb 2025Mar 2025Glasgow City1.2
David Lloyd Leisure Health Club, Stewarton Roadrooftop solarrooftop solar0.5approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024East Renfrewshire3.1
Fifty Pitches Placerooftop solarrooftop solar0.5approved, not builtupdated Dec 2023Aug 2023granted Dec 2023Dec 2023Glasgow City3.9
Helen Streetrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Jul 2023granted Oct 2023Nov 2023Glasgow City4.6
Hutchesons Grammar Schoolrooftop solarrooftop solar0.2operationalupdated May 2023Mar 2020granted Jun 2020May 2023Glasgow City4.7
Shipyard, Govan Roadrooftop solarrooftop solar0.8approved, not builtupdated Jul 2024Mar 2024granted Jul 2024Jul 2024Glasgow City5.2
Cpi Medicines Manufacturing Centre, Netherton Squarerooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jul 2023granted Jan 2024Mar 2024Renfrewshire5.8
Decathlon, Old Govan Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Dec 2023granted Mar 2024Apr 2024Renfrewshire5.9
Kelvin Hall Sports Arena, Argyle Streetrooftop solarrooftop solar0.6approved, not builtupdated Aug 2024Jun 2024granted Aug 2024Aug 2024Glasgow City6.4
Argyle Streetrooftop solarrooftop solar0.6approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025Glasgow City6.4
Lightyear Building, Marchburn Drive - Block A - Solar Panelsrooftop solarrooftop solar0.4application submittedupdated Mar 2026Jan 2026—Mar 2026Renfrewshire6.5
Shipyardrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Glasgow City6.6
Glasgow Airport Solar Farmbattery storagebattery storage—under constructionupdated May 2024Nov 2022granted Apr 2023May 2024Renfrewshire6.7
Sheriff Court Of Glasgow, Carlton Placerooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Glasgow City7.1
Glasgow High School, Crow Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Glasgow City7.5
Linn Products, Glasgow Roadsolar farmsolar farm0.5approved, not builtupdated Mar 2025Feb 2025granted Mar 2025Mar 2025East Renfrewshire7.8
Glasgow Royal Concert Hall, Sauchiehall Streetrooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Oct 2025granted Jan 2026Mar 2026Glasgow City7.9
Garscube Roadrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Jun 2023May 2023granted Jun 2023Jun 2023Glasgow City8.1
Clyde Gateway Developments Limited - D2 Grids Demonstrator Projectsolar farmsolar farm—application submitted may be out of dateupdated Feb 2022Dec 2022—Feb 2022South Lanarkshire8.1
Duke Street Solar Panelsrooftop solarrooftop solar—approved, not built may be out of dateupdated Mar 2021Feb 2021granted Mar 2021Mar 2021Glasgow City8.4
The Curran Building, St James Roadrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Dec 2022Aug 2022granted Nov 2022Dec 2022Glasgow City8.5
Dalmarnock Wastewater Treatment Worksrooftop solarrooftop solar—approved, not built may be out of dateupdated May 2021Apr 2021granted Jun 2021May 2021Glasgow City8.6
Clyde Gateway Trade Park, Dalmarnock Roadbattery storagebattery storage—application submittedMay 2026——South Lanarkshire8.8
Cartside Avenue, Inchinnanrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Oct 2022granted Feb 2023Mar 2023Renfrewshire8.9
Middleton Road, Linwoodbattery storagebattery storage—approved, not builtupdated Feb 2025Apr 2024granted Jan 2025Feb 2025Renfrewshire9.0
Bray Controls UK, Fountain Crescentrooftop solarrooftop solar0.2application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024Renfrewshire9.2
Allerdyce Roadrooftop solarrooftop solar0.2application withdrawnupdated Jun 2025Dec 2023—Jun 2025Glasgow City9.3
Balmore Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated May 2023May 2023granted Jul 2023May 2023Glasgow City9.7
Cunninghame Road, Farm Castle Industrial Estaterooftop solarrooftop solar0.2approved, not built may be out of dateupdated Sep 2022Aug 2022granted Sep 2022Sep 2022South Lanarkshire9.7
Morrison Bowmore Distillery, Carlisle Street Solar solar PV Systemrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Glasgow City9.8

Distance from the average position of the G53 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm71600104
Rooftop solar25221107.1
Wind farm5011215
Wind turbine300110
Battery storage21413022,064

MW in pipeline: pending, approved and under-construction capacity.

How Glasgow City decides solar, wind and battery applications

ApplicationsGlasgow CityUK
Decided applications (solar, wind, battery)2310,236
Refused0 (0%)19%
Solar refused0 of 1912%
Onshore wind refused0 of 145%
Battery storage refused0 of 316%
Median time from submission to decision13.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Glasgow City

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near G53, 12 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.