Broomloan Road (49.9 MW battery storage)

Broomloan Road is a 49.9 MW battery storage project in Glasgow City, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 October 2024, not yet built; the record was last updated on 28 October 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
28 October 2024record last updated
Glasgow Citycouncil area

Planning timeline

DateStage
22 March 2024Application submitted
4 October 2024Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
28 October 2024
Operator or applicant
Lifetime Property Limited
Planning authority
Glasgow City
Planning application reference
24/00714/FUL
Address (REPD)
322 Broomloan Road, Glasgow
Council area (by location)
Glasgow City
Time to decision
28 weeks
Name in REPD
Broomloan Road - Battery Energy Storage
REPD reference
17129

Earlier applications for this site

ApplicationMWSubmittedOutcome
Broomloan Road 22/00637/FUL49.915 March 2022replaced by a revised application

Who decides

ApplicationsGlasgow CityUK
Decided applications (solar, wind, battery)2310,236
Refused0 (0%)19%
Solar refused0 of 1912%
Onshore wind refused0 of 145%
Battery storage refused0 of 316%
Median time from submission to decision13.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Govan Battery Energy Storage Systembattery storage49.9application submitted0.5
Kennishead Roadbattery storage40application withdrawn4.8
Whitehill Energy Storagebattery storage200approved, not built4.9
Saturland Farm, Salterland Roadbattery storage60.8approved, not built6.3
Seath Road, Rutherglenbattery storage50refused6.5
Barnwell, Wright Streetbattery storage49.9refused6.6
Parkhouse Roadbattery storage24approved, not built6.6
Laigh Park Water Treatment Worksbattery storage49.5application submitted6.7
Caledonian Solar Parksolar farm18.4approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8551, -4.3137).