Seath Road, Rutherglen (50 MW battery storage)

Seath Road, Rutherglen is a 50 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 14 March 2024; the record was last updated on 2 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
refusedstatus in REPD
2 April 2024record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
21 September 2023Application submitted
14 March 2024Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
refused
Record last updated
2 April 2024
Operator or applicant
Green Power Consultants
Planning authority
South Lanarkshire
Planning application reference
P/23/1214
Address (REPD)
Southeast Side of Seath Road Rutherglen
Council area (by location)
South Lanarkshire
Time to decision
25 weeks
Name in REPD
Seath Road, Rutherglen - Battery Storage
REPD reference
14378

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Downiebrae Road, Rutherglenbattery storage150approved, not built0.5
Dalmarnock Roadbattery storage40approved, not built0.6
Whitehill Energy Storagebattery storage200approved, not built3.5
Highflat Battery Energy Storagebattery storage19.9application withdrawn4.9
Gilbertfield Farm, Gilbertfield Roadbattery storage40refused5.1
East Rogerton Cottage, Markethill Roadbattery storage55approved, not built6.2
Newton Farm, Westburn Roadbattery storage40refused6.2
Broomloan Roadbattery storage49.9approved, not built6.5
Govan Battery Energy Storage Systembattery storage49.9application submitted6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8341, -4.2161).