Highflat Battery Energy Storage (19.9 MW)

Highflat Battery Energy Storage is a 19.9 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 22 October 2018; the record was last updated on 23 November 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.9 MWbattery storage
application withdrawnstatus in REPD
23 November 2018record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
26 April 2018Application submitted
22 October 2018Application withdrawn

Project details

Technology
battery storage (stand-alone storage)
Capacity
19.9 MW
Status (REPD)
application withdrawn
Record last updated
23 November 2018
Operator or applicant
Highflat Energy Storage
Planning authority
South Lanarkshire
Planning application reference
P/18/0528
Address (REPD)
Land At, Cairnmuir Road, East Kilbride, Glasgow, Strathclyde
Council area (by location)
South Lanarkshire
REPD reference
7063

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Rogerton Cottage, Markethill Roadbattery storage55approved, not built1.9
Gilbertfield Farm, Gilbertfield Roadbattery storage40refused2.8
Seath Road, Rutherglenbattery storage50refused4.9
Dalmarnock Roadbattery storage40approved, not built5.0
Downiebrae Road, Rutherglenbattery storage150approved, not built5.0
Malcolmwood Farm, Loanend Roadbattery storage49.5application submitted5.1
Newton Farm, Westburn Roadbattery storage40refused5.7
Langlands Gate, East Kilbridebattery storage30refused6.4
Kelvin South Business Park, Hurlawcrook Roadbattery storage20application withdrawn6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7916, -4.1952).