Downiebrae Road, Rutherglen (150 MW battery storage)

Downiebrae Road, Rutherglen is a 150 MW battery storage project in Glasgow City, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 September 2025, not yet built; the record was last updated on 13 October 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

150 MWbattery storage
approved, not builtstatus in REPD
13 October 2025record last updated
Glasgow Citycouncil area

Planning timeline

DateStage
13 January 2025Application submitted
3 September 2025Section 36 consent granted (Scottish Ministers)
3 September 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
150 MW
Status (REPD)
approved, not built
Record last updated
13 October 2025
Operator or applicant
Battery Box Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005091
Address (REPD)
Downiebrae Road, Rutherglen
Council area (by location)
Glasgow City
Time to decision
33 weeks
Name in REPD
Downiebrae Road, Rutherglen - Battery Energy Storage System
REPD reference
16197

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Dalmarnock Roadbattery storage40approved, not built0.1
Seath Road, Rutherglenbattery storage50refused0.5
Whitehill Energy Storagebattery storage200approved, not built3.5
Gilbertfield Farm, Gilbertfield Roadbattery storage40refused5.0
Highflat Battery Energy Storagebattery storage19.9application withdrawn5.0
Newton Farm, Westburn Roadbattery storage40refused5.9
East Rogerton Cottage, Markethill Roadbattery storage55approved, not built6.2
Broomloan Roadbattery storage49.9approved, not built6.9
Govan Battery Energy Storage Systembattery storage49.9application submitted7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8362, -4.2085).