Solar, wind and battery projects near Rutherglen (G73)
57 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of G73 (South Lanarkshire): 6 are waiting for a planning decision, 39 approved but not yet running, 4 operational. The largest live scheme is Whitehill Energy Storage (200 MW battery storage, approved on 28 October 2024, not yet built), 5.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of G73
Projects of 1 MW and more (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Seath Road, Rutherglenbattery storage | battery storage | 50 | refusedupdated Apr 2024 | Sep 2023 | refused Mar 2024 | Apr 2024 | South Lanarkshire | 1.7 |
| Downiebrae Road, Rutherglenbattery storage | battery storage | 150 | approved, not builtupdated Oct 2025 | Jan 2025 | granted Sep 2025 | Oct 2025 | Glasgow City | 1.9 |
| Dalmarnock Roadbattery storage | battery storage | 40 | approved, not built may be out of dateupdated Mar 2021 | Sep 2021 | granted Feb 2022 | Mar 2021 | South Lanarkshire | 1.9 |
| Cathkin Braes Wind Farm (Castlemilk)wind turbine | wind turbine | 3 | operationalupdated Sep 2013 | Sep 2012 | granted Jan 2013 | Sep 2013 | South Lanarkshire | 2.5 |
| Castlemilk and Carmunnock Community Windpark Trustwind turbine | wind turbine | 2.5 | refusedupdated Mar 2015 | Aug 2013 | refused Nov 2013 | Mar 2015 | South Lanarkshire | 3.1 |
| Highflat Battery Energy Storagebattery storage | battery storage | 19.9 | application withdrawnupdated Nov 2018 | Apr 2018 | — | Nov 2018 | South Lanarkshire | 3.2 |
| Gilbertfield Farm, Gilbertfield Roadbattery storage | battery storage | 40 | refusedupdated Dec 2025 | Apr 2025 | refused Oct 2025 | Dec 2025 | South Lanarkshire | 3.7 |
| East Rogerton Cottage, Markethill Roadbattery storage | battery storage | 55 | approved, not builtupdated Jun 2026 | Sep 2025 | granted Feb 2026 | Jun 2026 | South Lanarkshire | 4.5 |
| Whitehill Energy Storagebattery storage | battery storage | 200 | approved, not builtupdated Dec 2024 | Oct 2022 | granted Oct 2024 | Dec 2024 | Glasgow City | 5.3 |
| Newton Farm, Westburn Roadbattery storage | battery storage | 40 | refusedupdated Apr 2026 | Jul 2025 | refused Feb 2026 | Apr 2026 | South Lanarkshire | 5.5 |
| Malcolmwood Farm, Loanend Roadbattery storage | battery storage | 49.5 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | South Lanarkshire | 6.5 |
| Govan Battery Energy Storage Systembattery storage | battery storage | 49.9 | application submittedupdated Mar 2025 | Feb 2025 | — | Mar 2025 | Glasgow City | 7.7 |
| Broomloan Roadbattery storage | battery storage | 49.9 | approved, not builtupdated Oct 2024 | Mar 2024 | granted Oct 2024 | Oct 2024 | Glasgow City | 7.8 |
| Kennishead Roadbattery storage | battery storage | 40 | application withdrawnupdated Mar 2026 | Jun 2025 | — | Mar 2026 | Glasgow City | 7.8 |
| Glasgow Road, Eagleshambattery storage | battery storage | 40 | approved, not builtupdated May 2025 | Jan 2025 | granted Apr 2025 | May 2025 | East Renfrewshire | 8.9 |
| Langlands Gate, East Kilbridebattery storage | battery storage | 30 | refusedupdated Nov 2025 | May 2025 | refused Sep 2025 | Nov 2025 | South Lanarkshire | 9.5 |
| Dunwan Dam, Eaglesham Wind Farmwind farm | wind farm | 30 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | East Renfrewshire | 9.7 |
| Middleton Wind Farmwind farm | wind farm | 12 | operationalupdated Mar 2015 | Feb 2008 | granted Aug 2011 | Mar 2015 | East Renfrewshire | 9.8 |
| Kelvin South Business Park, Hurlawcrook Roadbattery storage | battery storage | 20 | application withdrawnupdated Sep 2025 | Aug 2024 | — | Sep 2025 | South Lanarkshire | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (38)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Cunninghame Road, Farm Castle Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Sep 2022 | Aug 2022 | granted Sep 2022 | Sep 2022 | South Lanarkshire | 1.4 |
| Clyde Gateway Trade Park, Dalmarnock Roadbattery storage | battery storage | — | application submitted | May 2026 | — | — | South Lanarkshire | 1.7 |
| Clyde Gateway Developments Limited - D2 Grids Demonstrator Projectsolar farm | solar farm | — | application submitted may be out of dateupdated Feb 2022 | Dec 2022 | — | Feb 2022 | South Lanarkshire | 2.0 |
| Dalmarnock Wastewater Treatment Worksrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated May 2021 | Apr 2021 | granted Jun 2021 | May 2021 | Glasgow City | 2.1 |
| Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSsolar farm | solar farm | 0.6 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | South Lanarkshire | 2.9 |
| Cambuslang Investment Park, Clydesmill Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Glasgow City | 3.0 |
| Westburn Drive, Cambuslangrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | South Lanarkshire | 3.0 |
| Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSbattery storage | battery storage | — | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Glasgow City | 3.1 |
| Sheriff Court Of Glasgow, Carlton Placerooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Glasgow City | 4.7 |
| Sainsburys, Kingsgate Retail Parkrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Sep 2023 | Aug 2023 | — | Sep 2023 | South Lanarkshire | 4.8 |
| Duke Street Solar Panelsrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Mar 2021 | Feb 2021 | granted Mar 2021 | Mar 2021 | Glasgow City | 4.8 |
| Hutchesons Grammar Schoolrooftop solar | rooftop solar | 0.2 | operationalupdated May 2023 | Mar 2020 | granted Jun 2020 | May 2023 | Glasgow City | 5.1 |
| The Curran Building, St James Roadrooftop solar | rooftop solar | 0.1 | approved, not built may be out of dateupdated Dec 2022 | Aug 2022 | granted Nov 2022 | Dec 2022 | Glasgow City | 5.3 |
| Glasgow Royal Concert Hall, Sauchiehall Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Oct 2025 | granted Jan 2026 | Mar 2026 | Glasgow City | 5.8 |
| Tennant Avenue College, East Kilbriderooftop solar | rooftop solar | 0.9 | under constructionupdated Dec 2022 | Sep 2022 | granted May 2023 | Dec 2022 | South Lanarkshire | 6.1 |
| Allers Wastewater Treatment Works, Barrie Roadsolar farm | solar farm | 0.2 | operationalupdated Feb 2025 | Feb 2024 | granted Apr 2024 | Feb 2025 | South Lanarkshire | 6.3 |
| Garscube Roadrooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | Glasgow City | 6.7 |
| Morrison Bowmore Distillery, Carlisle Street Solar solar PV Systemrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Glasgow City | 7.4 |
| Police Training And Recruitment Centre, Eaglesham Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | South Lanarkshire | 7.6 |
| David Lloyd Leisure Health Club, Stewarton Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2024 | Oct 2023 | granted Dec 2023 | Jan 2024 | East Renfrewshire | 7.6 |
| Reynolds Building, Scottish Enterprise Technology Park- Solar Panlesrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | South Lanarkshire | 7.6 |
| Kelvin Hall Sports Arena, Argyle Streetrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 | Glasgow City | 7.7 |
| Argyle Streetrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Mar 2025 | Apr 2025 | Glasgow City | 7.7 |
| Linn Products, Glasgow Roadsolar farm | solar farm | 0.5 | approved, not builtupdated Mar 2025 | Feb 2025 | granted Mar 2025 | Mar 2025 | East Renfrewshire | 7.9 |
| Helen Streetrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2023 | Jul 2023 | granted Oct 2023 | Nov 2023 | Glasgow City | 7.9 |
| Stroud Road East, Kilbriderooftop solar | rooftop solar | — | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | South Lanarkshire | 8.1 |
| International House, Stanley Boulevardrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jul 2023 | Jun 2023 | granted Jun 2023 | Jul 2023 | South Lanarkshire | 8.4 |
| Clyde Avenue, Bothwellsolar farm | solar farm | 0.7 | approved, not built may be out of dateupdated Apr 2023 | Oct 2022 | granted Mar 2023 | Apr 2023 | South Lanarkshire | 8.5 |
| Stanley Boulevard, Hamilton Tech Park - Roof Mounted Photovoltaic Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | South Lanarkshire | 8.5 |
| Balmore Roadrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated May 2023 | May 2023 | granted Jul 2023 | May 2023 | Glasgow City | 8.6 |
| Shipyard, Govan Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jul 2024 | Mar 2024 | granted Jul 2024 | Jul 2024 | Glasgow City | 8.7 |
| Manson Place, Kelvin Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Apr 2023 | granted Jun 2023 | Jul 2023 | South Lanarkshire | 8.7 |
| Glasgow Road, Blantyrerooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Feb 2023 | Nov 2022 | granted Feb 2023 | Feb 2023 | South Lanarkshire | 8.9 |
| Tannochside Drive, Tannochside Parkrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2022 | Oct 2022 | granted Nov 2022 | Nov 2022 | North Lanarkshire | 9.0 |
| Hollywood Bowl Showcase Leisure Park, Barrbridge Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Aug 2022 | granted Aug 2022 | Nov 2022 | North Lanarkshire | 9.4 |
| Buchanan Gate, Steppssolar farm | solar farm | 0.9 | under constructionupdated Oct 2025 | Apr 2024 | granted May 2024 | Oct 2025 | North Lanarkshire | 9.6 |
| Fifty Pitches Placerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2023 | Aug 2023 | granted Dec 2023 | Dec 2023 | Glasgow City | 9.7 |
| Glasgow Museums Resource Centre, Woodhead Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Nov 2024 | granted Feb 2025 | Mar 2025 | Glasgow City | 9.8 |
Distance from the average position of the G73 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 1 | 4 | 1 | 0 | 2.6 |
| Rooftop solar | 30 | 1 | 28 | 1 | 0 | 8.7 |
| Wind farm | 2 | 1 | 0 | 1 | 0 | 30 |
| Wind turbine | 2 | 0 | 0 | 1 | 1 | 0 |
| Battery storage | 17 | 3 | 7 | 0 | 4 | 634 |
MW in pipeline: pending, approved and under-construction capacity.
How South Lanarkshire decides solar, wind and battery applications
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
All projects in South Lanarkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near G73, 12 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.