Middleton Wind Farm (12 MW)

Middleton Wind Farm is a 12 MW wind farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 4 September 2013; the record was last updated on 25 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
operationalstatus in REPD
25 March 2015record last updated
East Renfrewshirecouncil area

Planning timeline

DateStage
11 February 2008Application submitted
16 August 2011Planning permission granted
29 May 2012Construction started
4 September 2013Operational

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
25 March 2015
Operator or applicant
Scottish Power Renewables
Planning authority
East Renfrewshire
Planning application reference
2008/0096/TP
Turbines
6
Address (REPD)
East Refrewshire, G77 6
Council area (by location)
East Renfrewshire
Time to decision
183 weeks
REPD reference
3702

Who decides

ApplicationsEast RenfrewshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused0 of 312%
Onshore wind refused3 of 1345%
Battery storage refused1 of 216%
Median time from submission to decision61.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Loganswell Farmwind farm16application withdrawn1.3
Moorhouse (Eaglesham)wind farm47.5refused on appeal3.1
Parkhouse Roadbattery storage24approved, not built3.5
Bonnyton, Kirkton Moor Roadsolar farm28approved, not built3.7
Moorshield Wind Farmwind farm15approved, not built4.0
Saturland Farm, Salterland Roadbattery storage60.8approved, not built4.0
Kennishead Roadbattery storage40application withdrawn4.3
Glasgow Road, Eagleshambattery storage40approved, not built4.8
Dunwan Dam, Eaglesham Wind Farmwind farm30application submitted5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7751, -4.3426).