Energy Projects Near You

Solar, wind and battery projects near Glasgow (G76)

61 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of G76 (East Renfrewshire): 5 are waiting for a planning decision, 32 approved but not yet running, 8 operational. The largest live scheme is Whitehill Energy Storage (200 MW battery storage, approved on 28 October 2024, not yet built), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

61projects within 10 km
5awaiting a decision
32approved, not running
8operational

Projects within 10 km of G76

Projects of 1 MW and more (36)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Glasgow Road, Eagleshambattery storagebattery storage40approved, not builtupdated May 2025Jan 2025granted Apr 2025May 2025East Renfrewshire2.9
Dunwan Dam, Eaglesham Wind Farmwind farmwind farm30application submittedupdated Sep 2025Aug 2025—Sep 2025East Renfrewshire4.1
Cathkin Braes Wind Farm (Castlemilk)wind turbinewind turbine3operationalupdated Sep 2013Sep 2012granted Jan 2013Sep 2013South Lanarkshire4.2
Bonnyton, Kirkton Moor Roadsolar farmsolar farm28approved, not builtupdated Apr 2026Jul 2025granted Feb 2026Apr 2026East Renfrewshire4.3
Moorhouse (Eaglesham)wind farmwind farm47.5refused on appealupdated Jan 2013Apr 2010refused Apr 2012Jan 2013East Renfrewshire4.3
Middleton Wind Farmwind farmwind farm12operationalupdated Mar 2015Feb 2008granted Aug 2011Mar 2015East Renfrewshire4.4
Castlemilk and Carmunnock Community Windpark Trustwind turbinewind turbine2.5refusedupdated Mar 2015Aug 2013refused Nov 2013Mar 2015South Lanarkshire4.5
Loganswell Farmwind farmwind farm16application withdrawnupdated Sep 2014Apr 2014—Sep 2014East Renfrewshire4.9
Highflat Battery Energy Storagebattery storagebattery storage19.9application withdrawnupdated Nov 2018Apr 2018—Nov 2018South Lanarkshire5.1
Kennishead Roadbattery storagebattery storage40application withdrawnupdated Mar 2026Jun 2025—Mar 2026Glasgow City5.4
Over Enoch Farmwind farmwind farm6.5abandonedupdated Dec 2012May 2003granted Sep 2004Dec 2012East Renfrewshire6.0
Ardoch and Over Enoch Wind Farm (Ardoch)wind farmwind farm7.2operationalupdated Oct 2016May 2012granted Jul 2012Oct 2016East Renfrewshire6.5
Parkhouse Roadbattery storagebattery storage24approved, not builtupdated Aug 2025Mar 2024granted Aug 2025Aug 2025Glasgow City6.6
Ardoch Farm (East Renfrewshire)wind farmwind farm3.9abandonedupdated Dec 2011Jan 2003granted Sep 2004Dec 2011East Renfrewshire6.6
East Rogerton Cottage, Markethill Roadbattery storagebattery storage55approved, not builtupdated Jun 2026Sep 2025granted Feb 2026Jun 2026South Lanarkshire6.7
Saturland Farm, Salterland Roadbattery storagebattery storage60.8approved, not builtupdated Apr 2025Nov 2023granted Dec 2024Apr 2025Glasgow City6.9
Moorshield Wind Farmwind farmwind farm15approved, not builtupdated Feb 2026Sep 2023granted Sep 2024Feb 2026East Renfrewshire7.1
Seath Road, Rutherglenbattery storagebattery storage50refusedupdated Apr 2024Sep 2023refused Mar 2024Apr 2024South Lanarkshire7.3
Ardoch and Over Enoch Wind Farm (Over Enoch)wind farmwind farm4.3operationalupdated Oct 2016Sep 2011granted Apr 2012Oct 2016East Renfrewshire7.6
Downiebrae Road, Rutherglenbattery storagebattery storage150approved, not builtupdated Oct 2025Jan 2025granted Sep 2025Oct 2025Glasgow City7.7
Dalmarnock Roadbattery storagebattery storage40approved, not built may be out of dateupdated Mar 2021Sep 2021granted Feb 2022Mar 2021South Lanarkshire7.8
Langlands Gate, East Kilbridebattery storagebattery storage30refusedupdated Nov 2025May 2025refused Sep 2025Nov 2025South Lanarkshire7.9
Gilbertfield Farm, Gilbertfield Roadbattery storagebattery storage40refusedupdated Dec 2025Apr 2025refused Oct 2025Dec 2025South Lanarkshire7.9
Kelvin South Business Park, Hurlawcrook Roadbattery storagebattery storage20application withdrawnupdated Sep 2025Aug 2024—Sep 2025South Lanarkshire8.2
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storagebattery storage50approved, not builtupdated Jan 2025Apr 2021granted Jan 2025Jan 2025East Renfrewshire8.4
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farmsolar farm40approved, not builtupdated Jan 2025Apr 2021granted Jan 2025Jan 2025East Renfrewshire8.4
Govan Battery Energy Storage Systembattery storagebattery storage49.9application submittedupdated Mar 2025Feb 2025—Mar 2025Glasgow City8.7
Land East Of Shieldhill Farmwind farmwind farm18refused on appealupdated Nov 2018Jan 2015refused Mar 2018Nov 2018East Renfrewshire8.7
Land associated with Rawhead Farmwind turbinewind turbine1.5application withdrawnupdated May 2016Oct 2014—May 2016South Lanarkshire8.9
Broomloan Roadbattery storagebattery storage49.9approved, not builtupdated Oct 2024Mar 2024granted Oct 2024Oct 2024Glasgow City9.0
Land associated with Lairfadwind turbinewind turbine1.5application withdrawnupdated May 2016Oct 2014—May 2016South Lanarkshire9.2
Myres Hillwind farmwind farm1.8operationalupdated Nov 2001May 1999granted Aug 2001Nov 2001East Renfrewshire9.5
Myres Hill Wind Turbine Test Centrewind farmwind farm1application withdrawnupdated Sep 2019Feb 2019—Sep 2019East Renfrewshire9.5
National Wind Turbine Test Sitewind farmwind farm4.7operationalupdated Nov 2009Aug 1999granted Aug 2000Nov 2009East Renfrewshire9.6
Crutherland Farm Wind Turbinewind turbinewind turbine2refusedupdated Dec 2014Apr 2014refused Nov 2014Dec 2014South Lanarkshire9.9
Whitehill Energy Storagebattery storagebattery storage200approved, not builtupdated Dec 2024Oct 2022granted Oct 2024Dec 2024Glasgow City9.9
Smaller schemes under 1 MW, mostly rooftop solar (25)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Linn Products, Glasgow Roadsolar farmsolar farm0.5approved, not builtupdated Mar 2025Feb 2025granted Mar 2025Mar 2025East Renfrewshire1.7
Police Training And Recruitment Centre, Eaglesham Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023South Lanarkshire3.5
Tennant Avenue College, East Kilbriderooftop solarrooftop solar0.9under constructionupdated Dec 2022Sep 2022granted May 2023Dec 2022South Lanarkshire3.9
David Lloyd Leisure Health Club, Stewarton Roadrooftop solarrooftop solar0.5approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024East Renfrewshire4.0
Hutchesons Grammar Schoolrooftop solarrooftop solar0.2operationalupdated May 2023Mar 2020granted Jun 2020May 2023Glasgow City6.6
Sainsburys, Kingsgate Retail Parkrooftop solarrooftop solar—application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023South Lanarkshire6.6
Glasgow Museums Resource Centre, Woodhead Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Nov 2024granted Feb 2025Mar 2025Glasgow City6.8
Clyde Gateway Developments Limited - D2 Grids Demonstrator Projectsolar farmsolar farm—application submitted may be out of dateupdated Feb 2022Dec 2022—Feb 2022South Lanarkshire7.1
Stroud Road East, Kilbriderooftop solarrooftop solar—approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025South Lanarkshire7.1
Reynolds Building, Scottish Enterprise Technology Park- Solar Panlesrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023South Lanarkshire7.3
Clyde Gateway Trade Park, Dalmarnock Roadbattery storagebattery storage—application submittedMay 2026——South Lanarkshire7.4
Dalmarnock Wastewater Treatment Worksrooftop solarrooftop solar—approved, not built may be out of dateupdated May 2021Apr 2021granted Jun 2021May 2021Glasgow City7.6
Cunninghame Road, Farm Castle Industrial Estaterooftop solarrooftop solar0.2approved, not built may be out of dateupdated Sep 2022Aug 2022granted Sep 2022Sep 2022South Lanarkshire7.7
Manson Place, Kelvin Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Jul 2023Apr 2023granted Jun 2023Jul 2023South Lanarkshire7.9
Sheriff Court Of Glasgow, Carlton Placerooftop solarrooftop solar0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Glasgow City8.5
Allers Wastewater Treatment Works, Barrie Roadsolar farmsolar farm0.2operationalupdated Feb 2025Feb 2024granted Apr 2024Feb 2025South Lanarkshire8.7
Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSsolar farmsolar farm0.6approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026South Lanarkshire8.7
Westburn Drive, Cambuslangrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023South Lanarkshire8.9
Scottish Fire & Rescue Service, Westburn Drive Solar Array & BESSbattery storagebattery storage—approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Glasgow City9.0
Cambuslang Investment Park, Clydesmill Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Glasgow City9.2
Helen Streetrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Jul 2023granted Oct 2023Nov 2023Glasgow City9.2
Duke Street Solar Panelsrooftop solarrooftop solar—approved, not built may be out of dateupdated Mar 2021Feb 2021granted Mar 2021Mar 2021Glasgow City9.4
Glasgow Royal Concert Hall, Sauchiehall Streetrooftop solarrooftop solar0.2approved, not builtupdated Mar 2026Oct 2025granted Jan 2026Mar 2026Glasgow City9.8
The Curran Building, St James Roadrooftop solarrooftop solar0.1approved, not built may be out of dateupdated Dec 2022Aug 2022granted Nov 2022Dec 2022Glasgow City9.8
Fifty Pitches Placerooftop solarrooftop solar0.5approved, not builtupdated Dec 2023Aug 2023granted Dec 2023Dec 2023Glasgow City9.9

Distance from the average position of the G76 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6141069
Rooftop solar19117104.6
Wind farm13115245
Wind turbine500120
Battery storage1821003720

MW in pipeline: pending, approved and under-construction capacity.

How East Renfrewshire decides solar, wind and battery applications

ApplicationsEast RenfrewshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused0 of 312%
Onshore wind refused3 of 1345%
Battery storage refused1 of 216%
Median time from submission to decision61.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in East Renfrewshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near G76, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.