Ardoch and Over Enoch Wind Farm (Ardoch) (7.2 MW)
Ardoch and Over Enoch Wind Farm (Ardoch) is a 7.2 MW wind farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 November 2014; the record was last updated on 25 October 2016.
7.2 MWwind farm
operationalstatus in REPD
25 October 2016record last updated
East Renfrewshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 May 2012 | Application submitted |
| 9 July 2012 | Planning permission granted |
| 5 November 2013 | Construction started |
| 12 November 2014 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 7.2 MW
- Status (REPD)
- operational
- Record last updated
- 25 October 2016
- Operator or applicant
- 2020 Renewables/ NTR
- Planning authority
- East Renfrewshire
- Planning application reference
- 2012/0331/TP
- Turbines
- 3
- Turbine height
- 110 m
- Address (REPD)
- Ardoch Farm, Over Enoch Road, Eaglesham, East Renfrewshire
- Council area (by location)
- East Renfrewshire
- Time to decision
- 7 weeks
- REPD reference
- 3925
Who decides
| Applications | East Renfrewshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 18 | 10,236 |
| Refused | 4 (22%) | 19% |
| Solar refused | 0 of 3 | 12% |
| Onshore wind refused | 3 of 13 | 45% |
| Battery storage refused | 1 of 2 | 16% |
| Median time from submission to decision | 61.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Over Enoch Farm | wind farm | 6.5 | abandoned | 0.5 |
| Dunwan Dam, Eaglesham Wind Farm | wind farm | 30 | application submitted | 2.6 |
| Glasgow Road, Eaglesham | battery storage | 40 | approved, not built | 3.8 |
| Whitelee | wind farm | 322 | operational | 4.6 |
| Bonnyton, Kirkton Moor Road | solar farm | 28 | approved, not built | 4.8 |
| Whitelee Windfarm Extension Phase 3 | wind farm | 12 | refused on appeal | 5.2 |
| Whitelee Windfarm Extension Phase 1 | wind farm | 108 | operational | 5.2 |
| Moorhouse (Eaglesham) | wind farm | 47.5 | refused on appeal | 5.4 |
| Langlands Gate, East Kilbride | battery storage | 30 | refused | 5.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.72, -4.2537).