Energy Projects Near You

Whitelee Windfarm Extension Phase 1 (108 MW)

Whitelee Windfarm Extension Phase 1 is a 108 MW wind farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 October 2012; the record was last updated on 22 April 2013. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

108 MWwind farm
operationalstatus in REPD
22 April 2013record last updated
East Renfrewshirecouncil area

Planning timeline

DateStage
1 April 2008Application submitted
20 May 2009Section 36 consent granted (Scottish Ministers)
1 December 2010Construction started
31 October 2012Operational

Project details

Technology
wind farm
Capacity
108 MW
Status (REPD)
operational
Record last updated
22 April 2013
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
36
Address (REPD)
Eaglesham Moor, to the south of Glasgow
Council area (by location)
East Renfrewshire
Time to decision
59 weeks
REPD reference
3981

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitelee Windfarm Extension Phase 3wind farm12refused on appeal<0.1
Whiteleewind farm322operational0.7
East Kingswellwind farm26refused4.5
Whitelee Windfarm Extension phase 2wind farm109operational4.6
Ardoch and Over Enoch Wind Farm (Ardoch)wind farm7.2operational5.2
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farm40approved, not built5.3
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storage50approved, not built5.3
West Browncastlewind farm30operational5.3
Over Enoch Farmwind farm6.5abandoned5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6772, -4.2868).