Over Enoch Farm (6.5 MW wind farm)
Over Enoch Farm is a 6.5 MW wind farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 6 December 2012.
6.5 MWwind farm
abandonedstatus in REPD
6 December 2012record last updated
East Renfrewshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 8 May 2003 | Application submitted |
| 2 September 2004 | Planning permission granted |
| 2 September 2018 | Permission expired |
Project details
- Technology
- wind farm
- Capacity
- 6.5 MW
- Status (REPD)
- abandoned
- Record last updated
- 6 December 2012
- Operator or applicant
- Private Developer
- Planning authority
- East Renfrewshire
- Planning application reference
- 2003/0350
- Turbines
- 5
- Address (REPD)
- Over Enoch Farm Eaglesham East Renfrewshire
- Council area (by location)
- East Renfrewshire
- Time to decision
- 69 weeks
- REPD reference
- 4016
Who decides
| Applications | East Renfrewshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 18 | 10,236 |
| Refused | 4 (22%) | 19% |
| Solar refused | 0 of 3 | 12% |
| Onshore wind refused | 3 of 13 | 45% |
| Battery storage refused | 1 of 2 | 16% |
| Median time from submission to decision | 61.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Ardoch and Over Enoch Wind Farm (Ardoch) | wind farm | 7.2 | operational | 0.5 |
| Dunwan Dam, Eaglesham Wind Farm | wind farm | 30 | application submitted | 2.0 |
| Glasgow Road, Eaglesham | battery storage | 40 | approved, not built | 3.3 |
| Bonnyton, Kirkton Moor Road | solar farm | 28 | approved, not built | 4.3 |
| Whitelee | wind farm | 322 | operational | 4.9 |
| Moorhouse (Eaglesham) | wind farm | 47.5 | refused on appeal | 4.9 |
| Whitelees Hydrogen Production Facility, Solar Farm & Battery Storage | solar farm | 40 | approved, not built | 5.4 |
| Whitelees Hydrogen Production Facility, Solar Farm & Battery Storage | battery storage | 50 | approved, not built | 5.4 |
| Whitelee Windfarm Extension Phase 3 | wind farm | 12 | refused on appeal | 5.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7235, -4.2592).