Whitelee (322 MW wind farm)

Whitelee is a 322 MW wind farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 December 2007; the record was last updated on 20 May 2010. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

How it works ↓

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

322 MWwind farm
operationalstatus in REPD
20 May 2010record last updated
East Renfrewshirecouncil area

Planning timeline

DateStage
23 January 2002Application submitted
1 April 2006Section 36 consent granted (Scottish Ministers)
1 December 2006Construction started
14 December 2007Operational

Project details

Technology
wind farm
Capacity
322 MW
Status (REPD)
operational
Record last updated
20 May 2010
Operator or applicant
CRE Energy/ Scottish Power
Planning authority
Scottish Government (S36)
Planning application reference
2002/0001/EB
Turbines
140
Address (REPD)
Eaglesham Moor, Whitelee Forest, Fenwick Moor, East Kilbride, South of Glasgow
Council area (by location)
East Renfrewshire
Time to decision
218 weeks
REPD reference
3489

Whitelee is an onshore wind farm on Eaglesham Moor in East Renfrewshire, south of Glasgow: 322 MW, 140 turbines, with the first phase operational since December 2007. The applicant in the REPD is listed as CRE Energy / Scottish Power. Because the capacity exceeds 50 MW, the decision was taken by Scottish Ministers under Section 36 of the Electricity Act, bypassing the council. The database's information on it is out of date: the Whitelee record was last updated on 20 May 2010.

The application was submitted on 23 January 2002. Section 36 consent from the Scottish Government came on 1 April 2006, after 218 weeks. For comparison: across all 334 decided applications to the Scottish Government, the median time awaiting a decision was 127 weeks, and 18% were refused. So Whitelee waited considerably longer than usual, but once consent was granted things moved quickly: construction began on 1 December 2006, and the wind farm started generating on 14 December 2007. How Section 36 decisions work in general is set out on the Scotland page.

Extensions and other projects nearby

Extensions are recorded in the database as separate projects, so you cannot add their capacity to the first phase as a single figure. Whitelee Windfarm Extension Phase 1 at 108 MW and Phase 2 at 109 MW are operational, both between 0.7 and 5.2 km from the original site. A third phase (Phase 3) of 12 MW was refused on appeal. Within a 10 km radius there are other wind farms, as well as the Whitelees Hydrogen Production Facility: hydrogen production with a 40 MW solar component and 50 MW of battery storage, approved but not built. All projects in the area are listed on the East Renfrewshire page, and neighbouring sites can be found via postcode district, for example KA17 (Darvel). Statuses and dates here come from the July 2026 extract of the REPD; the database may lag behind decisions, and decisions made after the extract are not shown on the site.

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitelee Windfarm Extension Phase 3wind farm12refused on appeal0.7
Whitelee Windfarm Extension Phase 1wind farm108operational0.7
Ardoch and Over Enoch Wind Farm (Ardoch)wind farm7.2operational4.6
Over Enoch Farmwind farm6.5abandoned4.9
East Kingswellwind farm26refused4.9
West Browncastlewind farm30operational5.0
Whitelee Windfarm Extension phase 2wind farm109operational5.2
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storage50approved, not built5.3
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farm40approved, not built5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6812, -4.2791).