Solar, wind and battery projects near Darvel (KA17)
21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KA17 (East Ayrshire): 6 approved but not yet running, 8 operational. The largest live scheme is Bankend Rig III Wind Farm (66 MW wind farm, approved on 21 November 2025, not yet built), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of KA17
Projects of 1 MW and more (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Whitelee Windfarm Extension phase 2wind farm | wind farm | 109 | operationalupdated Apr 2013 | May 2009 | granted Dec 2009 | Apr 2013 | East Ayrshire | 4.0 |
| Calder Water Community Wind Farmwind farm | wind farm | 28 | operationalupdated Mar 2015 | Aug 2009 | granted Nov 2011 | Mar 2015 | South Lanarkshire | 5.2 |
| Alton Muirhouse Farmwind farm | wind farm | 6.8 | refused on appealupdated Dec 2018 | Dec 2015 | refused Jun 2018 | Dec 2018 | East Ayrshire | 6.3 |
| Mill Rig Wind Farmwind farm | wind farm | 36 | under constructionupdated Mar 2025 | Jun 2021 | granted Mar 2024 | Mar 2025 | South Lanarkshire | 6.6 |
| West Browncastlewind farm | wind farm | 30 | operationalupdated Aug 2014 | Oct 2010 | granted Jul 2012 | Aug 2014 | South Lanarkshire | 6.9 |
| Whitelee Windfarm Extension Phase 1wind farm | wind farm | 108 | operationalupdated Apr 2013 | Apr 2008 | granted May 2009 | Apr 2013 | East Renfrewshire | 7.4 |
| Whitelee Windfarm Extension Phase 3wind farm | wind farm | 12 | refused on appealupdated Nov 2016 | Aug 2012 | refused Oct 2016 | Nov 2016 | East Renfrewshire | 7.4 |
| Whiteleewind farm | wind farm | 322 | operationalupdated May 2010 | Jan 2002 | granted Apr 2006 | May 2010 | East Renfrewshire | 7.8 |
| Cowans Lawwind farm | wind farm | 49.9 | refusedupdated Jun 2019 | Apr 2010 | refused Nov 2010 | Jun 2019 | East Ayrshire | 8.1 |
| Sneddon Law Community Wind Farmwind farm | wind farm | 45 | under constructionupdated Sep 2022 | Jan 2012 | granted Feb 2013 | Sep 2022 | East Ayrshire | 8.1 |
| Bankend Rig II Wind Farmwind farm | wind farm | 10.2 | approved, not builtupdated Oct 2025 | Jul 2021 | granted Jun 2025 | Oct 2025 | South Lanarkshire | 8.4 |
| National Wind Turbine Test Sitewind farm | wind farm | 4.7 | operationalupdated Nov 2009 | Aug 1999 | granted Aug 2000 | Nov 2009 | East Renfrewshire | 8.9 |
| Myres Hill Wind Turbine Test Centrewind farm | wind farm | 1 | application withdrawnupdated Sep 2019 | Feb 2019 | — | Sep 2019 | East Renfrewshire | 9.0 |
| Myres Hillwind farm | wind farm | 1.8 | operationalupdated Nov 2001 | May 1999 | granted Aug 2001 | Nov 2001 | East Renfrewshire | 9.0 |
| Low Drumclog Farm, Drumclog - 3 Wind Turbineswind farm | wind farm | 20 | approved, not builtupdated Jun 2026 | Feb 2022 | granted Oct 2024 | Jun 2026 | South Lanarkshire | 9.2 |
| Bankend Rig III Wind Farmwind farm | wind farm | 66 | approved, not builtupdated Jan 2026 | Jan 2024 | granted Nov 2025 | Jan 2026 | South Lanarkshire | 9.3 |
| Dungavel House, IRC Muirkirk Road Wind Farmwind farm | wind farm | 11.4 | approved, not builtupdated Oct 2025 | Aug 2022 | granted Jan 2025 | Oct 2025 | South Lanarkshire | 9.3 |
| East Kingswellwind farm | wind farm | 26 | refusedupdated Nov 2015 | May 2010 | refused Dec 2010 | Nov 2015 | East Ayrshire | 9.6 |
| Bankend Rigwind farm | wind farm | 14.3 | operationalupdated May 2013 | Jun 2006 | granted Jun 2011 | May 2013 | South Lanarkshire | 9.8 |
| Stoney Hill Farmwind turbine | wind turbine | 2 | permission expiredupdated Sep 2020 | Nov 2015 | granted Jul 2016 | Sep 2020 | South Lanarkshire | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Stoneyhill Farm Wind turbineswind farm | wind farm | — | application withdrawnupdated Jun 2024 | Sep 2022 | — | Jun 2024 | South Lanarkshire | 8.4 |
Distance from the average position of the KA17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Wind farm | 20 | 0 | 6 | 8 | 4 | 189 |
| Wind turbine | 1 | 0 | 0 | 0 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How East Ayrshire decides solar, wind and battery applications
| Applications | East Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 36 | 10,236 |
| Refused | 17 (47%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 17 of 25 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 95.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 4 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.