Solar, wind and battery projects near Kilmarnock (KA3)
18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KA3 (East Ayrshire): 1 is waiting for a planning decision, 8 approved but not yet running, 3 operational. The largest live scheme is Kilmarnock Battery Energy Storage System (500 MW battery storage, approved on 7 April 2025, not yet built), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of KA3
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Holmquarry Roadbattery storage | battery storage | 60.4 | approved, not builtupdated Oct 2025 | Mar 2024 | granted Jul 2025 | Oct 2025 | East Ayrshire | 5.3 |
| Cowans Lawwind farm | wind farm | 49.9 | refusedupdated Jun 2019 | Apr 2010 | refused Nov 2010 | Jun 2019 | East Ayrshire | 6.4 |
| Sneddon Law Community Wind Farmwind farm | wind farm | 45 | under constructionupdated Sep 2022 | Jan 2012 | granted Feb 2013 | Sep 2022 | East Ayrshire | 6.4 |
| Kilmarnock South Substationbattery storage | battery storage | 300 | operationalupdated Mar 2026 | Feb 2022 | — | Mar 2026 | East Ayrshire | 7.7 |
| Blair Data Centrewind farm | wind farm | 13.8 | refused on appealupdated Aug 2016 | Mar 2015 | refused Jul 2016 | Aug 2016 | East Ayrshire | 7.8 |
| Alton Muirhouse Farmwind farm | wind farm | 6.8 | refused on appealupdated Dec 2018 | Dec 2015 | refused Jun 2018 | Dec 2018 | East Ayrshire | 8.1 |
| Glenouther Renewable Energy Parkwind farm | wind farm | 30 | refused on appealupdated Nov 2018 | Aug 2015 | refused May 2016 | Nov 2018 | East Ayrshire | 8.1 |
| Inchbean Farm, Treeswoodhead Roadbattery storage | battery storage | 60 | approved, not builtupdated Jul 2025 | Nov 2023 | granted Jun 2025 | Jul 2025 | East Ayrshire | 8.4 |
| Kilmarnock Battery Energy Storage Systembattery storage | battery storage | 500 | approved, not builtupdated Jun 2026 | Sep 2023 | granted Apr 2025 | Jun 2026 | East Ayrshire | 9.0 |
| Olympic Business Park, Dundonald - 2 Wind Turbineswind farm | wind farm | 8.5 | refusedupdated Jan 2025 | Jan 2024 | refused Dec 2024 | Jan 2025 | South Ayrshire | 9.2 |
| Hillhouse Quarry, Railway Bridgesolar farm | solar farm | 3 | application submitted may be out of dateupdated Jun 2024 | Jun 2024 | — | Jun 2024 | South Ayrshire | 9.4 |
| GlaxoSmithKline Wind Project (Turbine 4)wind turbine | wind turbine | 2.5 | operationalupdated May 2015 | Nov 2012 | granted Jun 2013 | May 2015 | North Ayrshire | 9.6 |
| East Kingswellwind farm | wind farm | 26 | refusedupdated Nov 2015 | May 2010 | refused Dec 2010 | Nov 2015 | East Ayrshire | 9.8 |
| Glaxosmithkline Shewalton Roadsolar farm | solar farm | 19.9 | under constructionupdated Mar 2023 | Mar 2019 | granted Jun 2019 | Mar 2023 | North Ayrshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (4)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Aldi Foodstore, Rigg Streetrooftop solar | rooftop solar | — | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | East Ayrshire | 4.1 |
| Elmbank Drive Solar Panelsrooftop solar | rooftop solar | — | operationalupdated Dec 2021 | Jan 2021 | granted Aug 2021 | Dec 2021 | East Ayrshire | 4.1 |
| Kilmarnock Academy, Elmbank Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Oct 2023 | granted Nov 2023 | Nov 2023 | East Ayrshire | 4.1 |
| Moorfield North Industrial Park, Moorfieldrooftop solar | rooftop solar | — | approved, not builtupdated Feb 2021 | Jan 2021 | granted Mar 2021 | Feb 2021 | East Ayrshire | 5.2 |
Distance from the average position of the KA3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 2 | 1 | 1 | 0 | 0 | 22.9 |
| Rooftop solar | 4 | 0 | 3 | 1 | 0 | 0.2 |
| Wind farm | 7 | 0 | 1 | 0 | 6 | 45 |
| Wind turbine | 1 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 4 | 0 | 3 | 1 | 0 | 620 |
MW in pipeline: pending, approved and under-construction capacity.
How East Ayrshire decides solar, wind and battery applications
| Applications | East Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 36 | 10,236 |
| Refused | 17 (47%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 17 of 25 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 95.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 4 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KA3, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.