East Kingswell (26 MW wind farm)

East Kingswell is a 26 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 1 December 2010; the record was last updated on 24 November 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26 MWwind farm
refusedstatus in REPD
24 November 2015record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
25 May 2010Application submitted
1 December 2010Refused by the planning authority

Project details

Technology
wind farm
Capacity
26 MW
Status (REPD)
refused
Record last updated
24 November 2015
Operator or applicant
Scottish Power Renewables
Planning authority
East Ayrshire
Planning application reference
10/0485/PP
Turbines
7
Address (REPD)
Eaglesham Moor, East Ayrshire
Council area (by location)
East Ayrshire
Time to decision
27 weeks
REPD reference
2761

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storage50approved, not built3.2
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farm40approved, not built3.2
Land East Of Shieldhill Farmwind farm18refused on appeal3.4
Blair Data Centrewind farm13.8refused on appeal3.5
Whitelee Windfarm Extension Phase 3wind farm12refused on appeal4.5
Whitelee Windfarm Extension Phase 1wind farm108operational4.5
Glenouther Renewable Energy Parkwind farm30refused on appeal4.6
Whiteleewind farm322operational4.9
Sneddon Law Community Wind Farmwind farm45under construction5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.6844, -4.3573).