Whitelees Hydrogen Production Facility, Solar Farm & Battery Storage (40 MW)

Whitelees Hydrogen Production Facility, Solar Farm & Battery Storage is a 40 MW solar farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 January 2025, not yet built; the record was last updated on 20 January 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
20 January 2025record last updated
East Renfrewshirecouncil area

Planning timeline

DateStage
17 April 2021Application submitted
9 January 2025Section 36 consent granted (Scottish Ministers)
9 January 2030Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
20 January 2025
Operator or applicant
Scottish Power Renewables
Planning authority
Scottish Government (S36)
Planning application reference
ECU00002198
Site area
1.4 ha
Address (REPD)
Eaglesham
Council area (by location)
East Renfrewshire
Time to decision
195 weeks
REPD reference
8341

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storage50approved, not built<0.1
Land East Of Shieldhill Farmwind farm18refused on appeal0.9
East Kingswellwind farm26refused3.2
Moorshield Wind Farmwind farm15approved, not built3.7
Bonnyton, Kirkton Moor Roadsolar farm28approved, not built4.2
Moorhouse (Eaglesham)wind farm47.5refused on appeal4.4
Blair Data Centrewind farm13.8refused on appeal4.5
Glenouther Renewable Energy Parkwind farm30refused on appeal5.0
Whitelee Windfarm Extension Phase 3wind farm12refused on appeal5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7122, -4.3432).