Bonnyton, Kirkton Moor Road (28 MW solar farm)

Bonnyton, Kirkton Moor Road is a 28 MW solar farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 February 2026, not yet built; the record was last updated on 27 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWsolar farm
approved, not builtstatus in REPD
27 April 2026record last updated
East Renfrewshirecouncil area

Planning timeline

DateStage
11 July 2025Application submitted
11 February 2026Planning permission granted
11 February 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
28 MW
Status (REPD)
approved, not built
Record last updated
27 April 2026
Operator or applicant
Advance Construction(Scotland) Limited
Planning authority
East Renfrewshire
Planning application reference
2025/0405/TP
Site area
57.0 ha
Address (REPD)
Bonnyton (South Of Kirkton Moor Road And Bonnyton Golf Club) Eaglesham
Council area (by location)
East Renfrewshire
Time to decision
31 weeks
Name in REPD
Bonnyton, Kirkton Moor Road - Solar PV Panels
REPD reference
18664

Who decides

ApplicationsEast RenfrewshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused0 of 312%
Onshore wind refused3 of 1345%
Battery storage refused1 of 216%
Median time from submission to decision61.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Moorhouse (Eaglesham)wind farm47.5refused on appeal0.6
Glasgow Road, Eagleshambattery storage40approved, not built2.2
Dunwan Dam, Eaglesham Wind Farmwind farm30application submitted2.6
Loganswell Farmwind farm16application withdrawn2.8
Moorshield Wind Farmwind farm15approved, not built3.4
Middleton Wind Farmwind farm12operational3.7
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storage50approved, not built4.2
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farm40approved, not built4.2
Over Enoch Farmwind farm6.5abandoned4.3