Moorshield Wind Farm (15 MW)

Moorshield Wind Farm is a 15 MW wind farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 September 2024, not yet built; the record was last updated on 10 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
approved, not builtstatus in REPD
10 February 2026record last updated
East Renfrewshirecouncil area

Planning timeline

DateStage
14 September 2023Application submitted
25 September 2024Planning permission granted
25 September 2027Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
approved, not built
Record last updated
10 February 2026
Operator or applicant
Wind 2 / EDPR
Planning authority
East Renfrewshire
Planning application reference
2023/0542/TP
Turbines
3
Turbine height
150 m
Address (REPD)
Adj 630m E/O Shieldhill Farm, Ayr Road, Loganswell, Glasgow
Council area (by location)
East Renfrewshire
Time to decision
54 weeks
Contracts for Difference
AR7a
REPD reference
14958

Earlier applications for this site

ApplicationMWSubmittedOutcome
Moorshield Wind Farm 2020/0217/TP154 May 2020refused 13 October 2022

Who decides

ApplicationsEast RenfrewshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused0 of 312%
Onshore wind refused3 of 1345%
Battery storage refused1 of 216%
Median time from submission to decision61.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Loganswell Farmwind farm16application withdrawn2.7
Moorhouse (Eaglesham)wind farm47.5refused on appeal3.0
Land East Of Shieldhill Farmwind farm18refused on appeal3.2
Bonnyton, Kirkton Moor Roadsolar farm28approved, not built3.4
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farm40approved, not built3.7
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storage50approved, not built3.7
Middleton Wind Farmwind farm12operational4.0
Harelaw Renewable Energy Parkwind farm117refused4.9
Glenouther Renewable Energy Parkwind farm30refused on appeal5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7424, -4.3676).