Harelaw Renewable Energy Park (117 MW)

Harelaw Renewable Energy Park is a 117 MW wind farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 27 September 2013; the record was last updated on 7 February 2014. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

117 MWwind farm
refusedstatus in REPD
7 February 2014record last updated
East Renfrewshirecouncil area

Planning timeline

DateStage
19 May 2009Application submitted
27 September 2013Refused by the planning authority

Project details

Technology
wind farm
Capacity
117 MW
Status (REPD)
refused
Record last updated
7 February 2014
Operator or applicant
Gamesa Energy
Planning authority
Scottish Government (S36)
Planning application reference
not recorded
Turbines
39
Address (REPD)
Harelaw, East Renfrewshire
Council area (by location)
East Renfrewshire
Time to decision
227 weeks
REPD reference
4001

Earlier applications for this site

ApplicationMWSubmittedOutcome
Harelaw Renewable Energy Park Wind Turbines 2009/0304/EBC80—withdrawn 4 July 2011

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Neilston Wind Farmwind farm9.2operational1.5
Moorshield Wind Farmwind farm15approved, not built4.9
Neilston Greener Grid Park - Phase 2battery storage750approved, not built5.5
Neilstonbattery storage150approved, not built5.7
Glenouther Renewable Energy Parkwind farm30refused on appeal5.9
Loganswell Farmwind farm16application withdrawn6.0
Middleton Wind Farmwind farm12operational6.6
Blair Data Centrewind farm13.8refused on appeal7.0
Parkhouse Roadbattery storage24approved, not built7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7564, -4.4427).