Glenouther Renewable Energy Park (30 MW)

Glenouther Renewable Energy Park is a 30 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 25 May 2017; the record was last updated on 8 November 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWwind farm
refused on appealstatus in REPD
8 November 2018record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
10 August 2015Application submitted
13 May 2016Refused by the planning authority
12 August 2016Appeal lodged
25 May 2017Appeal refused

Project details

Technology
wind farm
Capacity
30 MW
Status (REPD)
refused on appeal
Record last updated
8 November 2018
Operator or applicant
Gamesa Energy Uk
Planning authority
East Ayrshire
Planning application reference
15/0584/PP
Appeal reference
PPA-190-2059
Turbines
12
Turbine height
127 m
Address (REPD)
Glenouther Renewable Energy Park, Clunch Road, Fenwick, Kilmarnock
Council area (by location)
East Ayrshire
Time to decision
40 weeks
REPD reference
5693

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blair Data Centrewind farm13.8refused on appeal1.3
Land East Of Shieldhill Farmwind farm18refused on appeal4.2
East Kingswellwind farm26refused4.6
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storage50approved, not built5.0
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farm40approved, not built5.0
Moorshield Wind Farmwind farm15approved, not built5.3
Harelaw Renewable Energy Parkwind farm117refused5.9
Neilston Wind Farmwind farm9.2operational6.1
Sneddon Law Community Wind Farmwind farm45under construction7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7051, -4.4214).