Energy Projects Near You

Solar, wind and battery projects near Newton Mearns (G77)

44 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of G77 (East Renfrewshire): 3 are waiting for a planning decision, 18 approved but not yet running, 8 operational. The largest live scheme is Neilston Greener Grid Park - Phase 2 (750 MW battery storage, approved on 13 August 2025, not yet built), 9.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

44projects within 10 km
3awaiting a decision
18approved, not running
8operational

Projects within 10 km of G77

Projects of 1 MW and more (35)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Middleton Wind Farmwind farmwind farm12operationalupdated Mar 2015Feb 2008granted Aug 2011Mar 2015East Renfrewshire0.7
Loganswell Farmwind farmwind farm16application withdrawnupdated Sep 2014Apr 2014—Sep 2014East Renfrewshire1.4
Moorhouse (Eaglesham)wind farmwind farm47.5refused on appealupdated Jan 2013Apr 2010refused Apr 2012Jan 2013East Renfrewshire2.7
Bonnyton, Kirkton Moor Roadsolar farmsolar farm28approved, not builtupdated Apr 2026Jul 2025granted Feb 2026Apr 2026East Renfrewshire3.2
Parkhouse Roadbattery storagebattery storage24approved, not builtupdated Aug 2025Mar 2024granted Aug 2025Aug 2025Glasgow City4.0
Moorshield Wind Farmwind farmwind farm15approved, not builtupdated Feb 2026Sep 2023granted Sep 2024Feb 2026East Renfrewshire4.1
Glasgow Road, Eagleshambattery storagebattery storage40approved, not builtupdated May 2025Jan 2025granted Apr 2025May 2025East Renfrewshire4.2
Kennishead Roadbattery storagebattery storage40application withdrawnupdated Mar 2026Jun 2025—Mar 2026Glasgow City4.4
Saturland Farm, Salterland Roadbattery storagebattery storage60.8approved, not builtupdated Apr 2025Nov 2023granted Dec 2024Apr 2025Glasgow City4.5
Dunwan Dam, Eaglesham Wind Farmwind farmwind farm30application submittedupdated Sep 2025Aug 2025—Sep 2025East Renfrewshire5.3
Land East Of Shieldhill Farmwind farmwind farm18refused on appealupdated Nov 2018Jan 2015refused Mar 2018Nov 2018East Renfrewshire6.8
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storagebattery storage50approved, not builtupdated Jan 2025Apr 2021granted Jan 2025Jan 2025East Renfrewshire6.9
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farmsolar farm40approved, not builtupdated Jan 2025Apr 2021granted Jan 2025Jan 2025East Renfrewshire6.9
Harelaw Renewable Energy Parkwind farmwind farm117refusedupdated Feb 2014May 2009refused Sep 2013Feb 2014East Renfrewshire7.2
Over Enoch Farmwind farmwind farm6.5abandonedupdated Dec 2012May 2003granted Sep 2004Dec 2012East Renfrewshire7.2
Ardoch and Over Enoch Wind Farm (Ardoch)wind farmwind farm7.2operationalupdated Oct 2016May 2012granted Jul 2012Oct 2016East Renfrewshire7.7
Cathkin Braes Wind Farm (Castlemilk)wind turbinewind turbine3operationalupdated Sep 2013Sep 2012granted Jan 2013Sep 2013South Lanarkshire7.8
Ardoch Farm (East Renfrewshire)wind farmwind farm3.9abandonedupdated Dec 2011Jan 2003granted Sep 2004Dec 2011East Renfrewshire7.9
Castlemilk and Carmunnock Community Windpark Trustwind turbinewind turbine2.5refusedupdated Mar 2015Aug 2013refused Nov 2013Mar 2015South Lanarkshire8.2
Neilston Additional Wind Turbinewind turbinewind turbine2.5permission expiredupdated Jul 2020Mar 2014granted Nov 2015Jul 2020East Renfrewshire8.2
Govan Battery Energy Storage Systembattery storagebattery storage49.9application submittedupdated Mar 2025Feb 2025—Mar 2025Glasgow City8.7
Ardoch and Over Enoch Wind Farm (Over Enoch)wind farmwind farm4.3operationalupdated Oct 2016Sep 2011granted Apr 2012Oct 2016East Renfrewshire8.7
Neilston Wind Farmwind farmwind farm9.2operationalupdated May 2017Nov 2009granted May 2011May 2017East Renfrewshire8.7
Highflat Battery Energy Storagebattery storagebattery storage19.9application withdrawnupdated Nov 2018Apr 2018—Nov 2018South Lanarkshire8.8
Neilston Greener Grid Park - Phase 2battery storagebattery storage750approved, not builtupdated Oct 2025Dec 2024granted Aug 2025Oct 2025Renfrewshire9.1
Broomloan Roadbattery storagebattery storage49.9approved, not builtupdated Oct 2024Mar 2024granted Oct 2024Oct 2024Glasgow City9.1
Glenouther Renewable Energy Parkwind farmwind farm30refused on appealupdated Nov 2018Aug 2015refused May 2016Nov 2018East Ayrshire9.4
Nether Carswell Cottage Wind Turbinewind turbinewind turbine4.2approved, not builtupdated Jul 2025Sep 2020granted May 2025Jul 2025East Ayrshire9.5
Nether Carswell Cottage Wind Turbinewind turbinewind turbine4.2abandonedupdated Jul 2025Apr 2024—Jul 2025East Ayrshire9.5
Myres Hillwind farmwind farm1.8operationalupdated Nov 2001May 1999granted Aug 2001Nov 2001East Renfrewshire9.7
National Wind Turbine Test Sitewind farmwind farm4.7operationalupdated Nov 2009Aug 1999granted Aug 2000Nov 2009East Renfrewshire9.7
Myres Hill Wind Turbine Test Centrewind farmwind farm1application withdrawnupdated Sep 2019Feb 2019—Sep 2019East Renfrewshire9.7
Blair Data Centrewind farmwind farm13.8refused on appealupdated Aug 2016Mar 2015refused Jul 2016Aug 2016East Ayrshire9.9
Seath Road, Rutherglenbattery storagebattery storage50refusedupdated Apr 2024Sep 2023refused Mar 2024Apr 2024South Lanarkshire9.9
Neilston Greener Grid Parkbattery storagebattery storage50under constructionupdated Mar 2026Jan 2021granted Apr 2022Mar 2026Renfrewshire9.9
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
David Lloyd Leisure Health Club, Stewarton Roadrooftop solarrooftop solar0.5approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024East Renfrewshire2.9
Linn Products, Glasgow Roadsolar farmsolar farm0.5approved, not builtupdated Mar 2025Feb 2025granted Mar 2025Mar 2025East Renfrewshire3.3
Glasgow Museums Resource Centre, Woodhead Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Nov 2024granted Feb 2025Mar 2025Glasgow City4.6
Police Training And Recruitment Centre, Eaglesham Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023South Lanarkshire6.4
Tennant Avenue College, East Kilbriderooftop solarrooftop solar0.9under constructionupdated Dec 2022Sep 2022granted May 2023Dec 2022South Lanarkshire7.4
Hutchesons Grammar Schoolrooftop solarrooftop solar0.2operationalupdated May 2023Mar 2020granted Jun 2020May 2023Glasgow City7.7
Fifty Pitches Placerooftop solarrooftop solar0.5approved, not builtupdated Dec 2023Aug 2023granted Dec 2023Dec 2023Glasgow City9.2
Helen Streetrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Jul 2023granted Oct 2023Nov 2023Glasgow City9.3
Clyde Gateway Developments Limited - D2 Grids Demonstrator Projectsolar farmsolar farm—application submitted may be out of dateupdated Feb 2022Dec 2022—Feb 2022South Lanarkshire9.5

Distance from the average position of the G77 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4130068.5
Rooftop solar706102.8
Wind farm17116545
Wind turbine501114.2
Battery storage1117011,075

MW in pipeline: pending, approved and under-construction capacity.

How East Renfrewshire decides solar, wind and battery applications

ApplicationsEast RenfrewshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused0 of 312%
Onshore wind refused3 of 1345%
Battery storage refused1 of 216%
Median time from submission to decision61.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in East Renfrewshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near G77, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.