Land East Of Shieldhill Farm (18 MW wind farm)

Land East Of Shieldhill Farm is an 18 MW wind farm project in East Renfrewshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 25 October 2018; the record was last updated on 27 November 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
refused on appealstatus in REPD
27 November 2018record last updated
East Renfrewshirecouncil area

Planning timeline

DateStage
8 January 2015Application submitted
14 March 2018Refused by the planning authority
13 June 2018Appeal lodged
25 October 2018Appeal refused

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
refused on appeal
Record last updated
27 November 2018
Operator or applicant
Coriolis Energy
Planning authority
East Renfrewshire
Planning application reference
2014/0820/TP
Appeal reference
PPA-220-2048
Turbines
6
Turbine height
115 m
Address (REPD)
Land East Of Shieldhill Farm, Moor Road, Newton Mearns, Glasgow, Strathclyde
Council area (by location)
East Renfrewshire
Time to decision
166 weeks
REPD reference
4947

Who decides

ApplicationsEast RenfrewshireUK
Decided applications (solar, wind, battery)1810,236
Refused4 (22%)19%
Solar refused0 of 312%
Onshore wind refused3 of 1345%
Battery storage refused1 of 216%
Median time from submission to decision61.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagebattery storage50approved, not built0.9
Whitelees Hydrogen Production Facility, Solar Farm & Battery Storagesolar farm40approved, not built0.9
Moorshield Wind Farmwind farm15approved, not built3.2
East Kingswellwind farm26refused3.4
Blair Data Centrewind farm13.8refused on appeal3.9
Glenouther Renewable Energy Parkwind farm30refused on appeal4.2
Bonnyton, Kirkton Moor Roadsolar farm28approved, not built4.5
Moorhouse (Eaglesham)wind farm47.5refused on appeal4.5
Loganswell Farmwind farm16application withdrawn5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.7145, -4.3573).