Energy Projects Near You

Parkhouse Road (24 MW battery storage)

Parkhouse Road is a 24 MW battery storage project in Glasgow City, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 August 2025, not yet built; the record was last updated on 19 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

24 MWbattery storage
approved, not builtstatus in REPD
19 August 2025record last updated
Glasgow Citycouncil area

Planning timeline

DateStage
6 March 2024Application submitted
8 August 2025Planning permission granted
8 August 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
24 MW
Status (REPD)
approved, not built
Record last updated
19 August 2025
Operator or applicant
GPC 1184 Limited
Planning authority
Glasgow City
Planning application reference
24/00342/FUL
Address (REPD)
S/O 557 Parkhouse Road
Council area (by location)
Glasgow City
Time to decision
74 weeks
Name in REPD
Parkhouse Road - Battery Energy Storage
REPD reference
16086

Who decides

ApplicationsGlasgow CityUK
Decided applications (solar, wind, battery)2310,236
Refused0 (0%)19%
Solar refused0 of 1912%
Onshore wind refused0 of 145%
Battery storage refused0 of 316%
Median time from submission to decision13.4 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Saturland Farm, Salterland Roadbattery storage60.8approved, not built0.5
Kennishead Roadbattery storage40application withdrawn2.5
Middleton Wind Farmwind farm12operational3.5
Loganswell Farmwind farm16application withdrawn4.6
Neilston Greener Grid Parkbattery storage50under construction5.9
Govan Battery Energy Storage Systembattery storage49.9application submitted6.1
Neilston Greener Grid Park - Phase 2battery storage750approved, not built6.3
Well Streetbattery storage49.5approved, not built6.4
Broomloan Roadbattery storage49.9approved, not built6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.8039, -4.3672).