Energy Projects Near You

Renewable energy projects in East Ayrshire

62 solar, wind or battery projects of 150 kW or more are located in East Ayrshire (REPD, July 2026 extract): 6 pending, 30 approved but not running, 6 operational and 13 refused. The council refused 17 of 36 decided applications (47%; UK 19%), with a median 96 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

62projects in the council area
6awaiting a decision
30approved, not running
47%of decisions refused

How East Ayrshire decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Projects in East Ayrshire

Projects of 1 MW and more (55)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Kilmarnock Battery Energy Storage Systembattery storagebattery storage500approved, not builtupdated Jun 2026Sep 2023granted Apr 2025Jun 2026
Kilmarnock South Substationbattery storagebattery storage300operationalupdated Mar 2026Feb 2022—Mar 2026
Kyle Windfarmwind farmwind farm255refusedupdated Jun 2010Oct 2004refused Oct 2008Jun 2010
South Kyle Wind Farmwind farmwind farm240operationalupdated Jan 2026Aug 2013granted Jun 2017Jan 2026
North Kyle Energy Projectwind farmwind farm206under constructionupdated Jun 2023Sep 2019granted Jun 2021Jun 2023
Whitelee Windfarm Extension phase 2wind farmwind farm109operationalupdated Apr 2013May 2009granted Dec 2009Apr 2013
Breezy Hill, North Kyle Forest Estatewind farmwind farm100application submittedupdated Jul 2025May 2025—Jul 2025
South Kyle Wind Farm 2wind farmwind farm92.4application submittedupdated Aug 2025May 2025—Aug 2025
Pencloe Wind Farmwind farmwind farm81under constructionupdated Feb 2026Feb 2015granted Dec 2018Feb 2026
Enoch Hillwind farmwind farm70operationalupdated Jun 2026Sep 2015granted Sep 2019Jun 2026
Greenburn Wind Parkwind farmwind farm67.2approved, not builtupdated Dec 2024Mar 2020granted Apr 2023Dec 2024
Galawhistlewind farmwind farm66operationalupdated Nov 2022Mar 2010granted Aug 2012Nov 2022
Lethans Wind Farm Extensionwind farmwind farm66approved, not builtupdated Feb 2026Dec 2021granted Aug 2024Feb 2026
Holmquarry Roadbattery storagebattery storage60.4approved, not builtupdated Oct 2025Mar 2024granted Jul 2025Oct 2025
Knockkippen Wind, Solar & Battery Farmwind farmwind farm60approved, not builtupdated Jul 2025Jun 2022granted Apr 2025Jul 2025
Inchbean Farm, Treeswoodhead Roadbattery storagebattery storage60approved, not builtupdated Jul 2025Nov 2023granted Jun 2025Jul 2025
Spireslack Windfarmwind farmwind farm59.6application withdrawnupdated May 2006May 2005—May 2006
Wind Farm at Sclenteuch Wind Farmwind farmwind farm54approved, not builtupdated Jan 2026Jul 2022granted Dec 2025Jan 2026
Chalmerstonwind farmwind farm50application withdrawnupdated Jun 2005Apr 2004—Jun 2005
Coylton Substation, Coyltonbattery storagebattery storage50under constructionupdated Sep 2024Nov 2023granted Feb 2024Sep 2024
Dersalloch Battery Storage Facilitybattery storagebattery storage50approved, not builtupdated Dec 2021Aug 2020granted Nov 2021Dec 2021
South Kyle Wind Farm 2battery storagebattery storage50application submittedupdated Aug 2025May 2025—Aug 2025
Cowans Lawwind farmwind farm49.9refusedupdated Jun 2019Apr 2010refused Nov 2010Jun 2019
Killoch Depot, Killoch Collierybattery storagebattery storage49.9approved, not built may be out of dateupdated Apr 2023Sep 2022granted Mar 2023Apr 2023
Glen Water Wind Farmwind farmwind farm49.9application submittedupdated Apr 2026Mar 2026—Apr 2026
The Drum Wind Farmwind farmwind farm49.6refusedupdated May 2026Feb 2023refused Oct 2025May 2026
Sneddon Law Community Wind Farmwind farmwind farm45under constructionupdated Sep 2022Jan 2012granted Feb 2013Sep 2022
Sclenteuch Wind Farmbattery storagebattery storage45approved, not builtupdated Jan 2026Jul 2022granted Dec 2025Jan 2026
Breezy Hill, North Kyle Forest Estatebattery storagebattery storage40application submittedupdated Jul 2025May 2025—Jul 2025
Hare Craig Windfarmwind farmwind farm36approved, not builtupdated May 2026Jan 2020granted Jul 2022May 2026
Over Hill Wind Farmwind farmwind farm36approved, not builtupdated Sep 2020Sep 2020granted Jul 2023Sep 2020
Polquhairn Wind Farmwind farmwind farm34.2application withdrawnupdated Apr 2026Jan 2021—Apr 2026
Glenouther Renewable Energy Parkwind farmwind farm30refused on appealupdated Nov 2018Aug 2015refused May 2016Nov 2018
Electricity Substation, Bardarrochbattery storagebattery storage29.9approved, not builtupdated May 2025Nov 2023granted Mar 2025May 2025
High Cumnock Wind Farmwind farmwind farm27.2refused on appealupdated Sep 2015Feb 2013refused Dec 2014Sep 2015
East Kingswellwind farmwind farm26refusedupdated Nov 2015May 2010refused Dec 2010Nov 2015
Wind Farm Extensionwind farmwind farm22.5application submittedupdated Apr 2025Dec 2024—Apr 2025
Garleffan Wind Farmwind farmwind farm21.6refused on appealupdated Jan 2018Apr 2013refused Oct 2016Jan 2018
Ashmark Hill Wind Farmwind farmwind farm21refused on appealupdated May 2015Jan 2012refused Sep 2014May 2015
Ashmark Hill Community Wind Farmwind farmwind farm21refusedupdated Nov 2018May 2018refused Sep 2018Nov 2018
Knockkippen Wind, Solar & Battery Farmsolar farmsolar farm20approved, not builtupdated Jul 2025Jun 2022granted Apr 2025Jul 2025
Burnhead Wind Farmwind farmwind farm18.4refused on appealupdated Mar 2014Nov 2011refused Jan 2013Mar 2014
Knockkippen Wind, Solar & Battery Farmbattery storagebattery storage16approved, not builtupdated Jul 2025Jun 2022granted Apr 2025Jul 2025
Hare Craig Windfarmbattery storagebattery storage13.9approved, not builtupdated May 2026Jan 2020granted Jul 2022May 2026
Blair Data Centrewind farmwind farm13.8refused on appealupdated Aug 2016Mar 2015refused Jul 2016Aug 2016
Enoch Hill, Dalmellingtonbattery storagebattery storage11approved, not builtupdated Aug 2025Sep 2023granted Jul 2025Aug 2025
Greenburn Wind Parkbattery storagebattery storage10approved, not builtupdated Dec 2024Mar 2020granted Apr 2023Dec 2024
Enoch Hill 2 Windfarmwind farmwind farm10approved, not builtupdated Feb 2026Sep 2023granted Jul 2025Feb 2026
Alton Muirhouse Farmwind farmwind farm6.8refused on appealupdated Dec 2018Dec 2015refused Jun 2018Dec 2018
Nether Carswell Cottage Wind Turbinewind turbinewind turbine4.2approved, not builtupdated Jul 2025Sep 2020granted May 2025Jul 2025
Nether Carswell Cottage Wind Turbinewind turbinewind turbine4.2abandonedupdated Jul 2025Apr 2024—Jul 2025
Skares Windfarmwind farmwind farm4application withdrawnupdated Nov 2013Jun 2005—Nov 2013
Knockshinnoch Wind Farmwind farmwind farm4approved, not built may be out of dateupdated Jan 2020Jul 2014granted May 2017Jan 2020
Little Kilmainwind farmwind farm2.2application withdrawnupdated Jun 2011——Jun 2011
Linburn Farmwind farmwind farm1.7permission expiredupdated Oct 2019Mar 2014granted Nov 2015Oct 2019
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Cummnock Waste Water Treatment Workssolar farmsolar farm0.5approved, not built may be out of dateupdated Jul 2022Mar 2023granted Jun 2023Jul 2022
Auldhouseburn Farm, Muirkirksolar farmsolar farm0.2approved, not built may be out of dateupdated May 2023Jan 2023granted May 2023May 2023
Kilmarnock Academy, Elmbank Driverooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023
High Park Farmwind farmwind farm—refused on appealupdated Nov 2018Jul 2017—Nov 2018
Moorfield North Industrial Park, Moorfieldrooftop solarrooftop solar—approved, not builtupdated Feb 2021Jan 2021granted Mar 2021Feb 2021
Elmbank Drive Solar Panelsrooftop solarrooftop solar—operationalupdated Dec 2021Jan 2021granted Aug 2021Dec 2021
Aldi Foodstore, Rigg Streetrooftop solarrooftop solar—approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025

Postcode districts in East Ayrshire

DistrictProjects within 10 kmPendingApprovedOperational
KA1253144
KA2273184
KA318183
KA413073
KA510081
KA6191140
KA1617048
KA1721068
KA1813160

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to East Ayrshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.