Solar, wind and battery projects near Drongan (KA6)
19 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KA6 (East Ayrshire): 1 is waiting for a planning decision, 14 approved but not yet running. The largest live scheme is Braston New Energy (500 MW battery storage, approved on 23 April 2025, not yet built), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of KA6
Projects of 1 MW and more (18)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Loch Fergus Farmbattery storage | battery storage | 45 | under constructionupdated Feb 2026 | Jul 2023 | granted Oct 2024 | Feb 2026 | South Ayrshire | 3.2 |
| Loch Fergus Farm Solar Farmsolar farm | solar farm | 40 | under constructionupdated Feb 2026 | Jul 2023 | granted Oct 2024 | Feb 2026 | South Ayrshire | 3.2 |
| Belston Battery Storagebattery storage | battery storage | 150 | approved, not builtupdated Jan 2026 | Nov 2024 | granted Jul 2025 | Jan 2026 | South Ayrshire | 5.4 |
| Electricity Substation, Bardarrochbattery storage | battery storage | 29.9 | approved, not builtupdated May 2025 | Nov 2023 | granted Mar 2025 | May 2025 | East Ayrshire | 5.6 |
| Coylton Substation, Coyltonbattery storage | battery storage | 50 | under constructionupdated Sep 2024 | Nov 2023 | granted Feb 2024 | Sep 2024 | East Ayrshire | 5.8 |
| Ailsa Hospitalwind turbine | wind turbine | 1 | application submitted may be out of dateupdated Aug 2022 | Jul 2022 | — | Aug 2022 | South Ayrshire | 6.0 |
| Polquhairn Wind Farmwind farm | wind farm | 34.2 | application withdrawnupdated Apr 2026 | Jan 2021 | — | Apr 2026 | East Ayrshire | 6.2 |
| Braston New Energybattery storage | battery storage | 500 | approved, not builtupdated Jul 2025 | Apr 2024 | granted Apr 2025 | Jul 2025 | South Ayrshire | 6.5 |
| Little Kilmainwind farm | wind farm | 2.2 | application withdrawnupdated Jun 2011 | — | — | Jun 2011 | East Ayrshire | 7.1 |
| Holmston Roadbattery storage | battery storage | 49.9 | under constructionupdated Aug 2025 | Mar 2023 | granted Jun 2023 | Aug 2025 | South Ayrshire | 7.2 |
| Killoch Depot, Killoch Collierybattery storage | battery storage | 49.9 | approved, not built may be out of dateupdated Apr 2023 | Sep 2022 | granted Mar 2023 | Apr 2023 | East Ayrshire | 7.7 |
| Knockkippen Wind, Solar & Battery Farmwind farm | wind farm | 60 | approved, not builtupdated Jul 2025 | Jun 2022 | granted Apr 2025 | Jul 2025 | East Ayrshire | 7.9 |
| Knockkippen Wind, Solar & Battery Farmsolar farm | solar farm | 20 | approved, not builtupdated Jul 2025 | Jun 2022 | granted Apr 2025 | Jul 2025 | East Ayrshire | 7.9 |
| Knockkippen Wind, Solar & Battery Farmbattery storage | battery storage | 16 | approved, not builtupdated Jul 2025 | Jun 2022 | granted Apr 2025 | Jul 2025 | East Ayrshire | 7.9 |
| Wind Farm at Sclenteuch Wind Farmwind farm | wind farm | 54 | approved, not builtupdated Jan 2026 | Jul 2022 | granted Dec 2025 | Jan 2026 | East Ayrshire | 9.0 |
| Sclenteuch Wind Farmbattery storage | battery storage | 45 | approved, not builtupdated Jan 2026 | Jul 2022 | granted Dec 2025 | Jan 2026 | East Ayrshire | 9.0 |
| Burnhead Wind Farmwind farm | wind farm | 18.4 | refused on appealupdated Mar 2014 | Nov 2011 | refused Jan 2013 | Mar 2014 | East Ayrshire | 9.1 |
| Kyle Windfarmwind farm | wind farm | 255 | refusedupdated Jun 2010 | Oct 2004 | refused Oct 2008 | Jun 2010 | East Ayrshire | 9.2 |
Smaller schemes under 1 MW, mostly rooftop solar (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Enterkine House, Annbanksolar farm | solar farm | 0.2 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | South Ayrshire | 7.2 |
Distance from the average position of the KA6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 0 | 3 | 0 | 0 | 60.2 |
| Wind farm | 6 | 0 | 2 | 0 | 2 | 114 |
| Wind turbine | 1 | 1 | 0 | 0 | 0 | 1 |
| Battery storage | 9 | 0 | 9 | 0 | 0 | 936 |
MW in pipeline: pending, approved and under-construction capacity.
How East Ayrshire decides solar, wind and battery applications
| Applications | East Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 36 | 10,236 |
| Refused | 17 (47%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 17 of 25 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 95.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 4 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KA6, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.