Loch Fergus Farm (45 MW battery storage)

Loch Fergus Farm is a 45 MW battery storage project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 June 2025; the record was last updated on 19 February 2026. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWbattery storage
under constructionstatus in REPD
19 February 2026record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
3 July 2023Application submitted
22 October 2024Section 36 consent granted (Scottish Ministers)
1 June 2025Construction started

Project details

Technology
battery storage (co-located with re)
Capacity
45 MW
Status (REPD)
under construction
Record last updated
19 February 2026
Operator or applicant
Locogen
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004855
Address (REPD)
Loch Fergus Farm
Council area (by location)
South Ayrshire
Time to decision
68 weeks
Name in REPD
Loch Fergus Farm - Energy Storage System
REPD reference
12274

Recorded together with Loch Fergus Farm Solar Farm (40 MW solar farm, under construction).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Belston Battery Storagebattery storage150approved, not built2.4
Braston New Energybattery storage500approved, not built3.3
Holmston Roadbattery storage49.9under construction4.0
Electricity Substation, Bardarrochbattery storage29.9approved, not built7.3
Coylton Substation, Coyltonbattery storage50under construction7.5
Killoch Depot, Killoch Collierybattery storage49.9approved, not built9.3
Polquhairn Wind Farmwind farm34.2application withdrawn9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4332, -4.5444).