Energy Projects Near You

Braston New Energy (500 MW battery storage)

Braston New Energy is a 500 MW battery storage project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 April 2025, not yet built; the record was last updated on 1 July 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWbattery storage
approved, not builtstatus in REPD
1 July 2025record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
3 April 2024Application submitted
23 April 2025Section 36 consent granted (Scottish Ministers)

Project details

Technology
battery storage (stand-alone storage)
Capacity
500 MW
Status (REPD)
approved, not built
Record last updated
1 July 2025
Operator or applicant
New Energy Partnership
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004995
Address (REPD)
A77, Masonhill, Alloway
Council area (by location)
South Ayrshire
Time to decision
55 weeks
REPD reference
15530

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Holmston Roadbattery storage49.9under construction1.6
Belston Battery Storagebattery storage150approved, not built2.5
Loch Fergus Farmbattery storage45under construction3.3
Loch Fergus Farm Solar Farmsolar farm40under construction3.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4431, -4.5945).