Energy Projects Near You

Solar, wind and battery projects near Ayr (KA8)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KA8 (South Ayrshire): 1 is waiting for a planning decision, 8 approved but not yet running. The largest live scheme is Braston New Energy (500 MW battery storage, approved on 23 April 2025, not yet built), 3.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
1awaiting a decision
8approved, not running
0operational

Projects within 10 km of KA8

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Holmston Roadbattery storagebattery storage49.9under constructionupdated Aug 2025Mar 2023granted Jun 2023Aug 2025South Ayrshire2.1
Braston New Energybattery storagebattery storage500approved, not builtupdated Jul 2025Apr 2024granted Apr 2025Jul 2025South Ayrshire3.4
Belston Battery Storagebattery storagebattery storage150approved, not builtupdated Jan 2026Nov 2024granted Jul 2025Jan 2026South Ayrshire4.0
Ailsa Hospitalwind turbinewind turbine1application submitted may be out of dateupdated Aug 2022Jul 2022—Aug 2022South Ayrshire4.4
Loch Fergus Farmbattery storagebattery storage45under constructionupdated Feb 2026Jul 2023granted Oct 2024Feb 2026South Ayrshire6.1
Loch Fergus Farm Solar Farmsolar farmsolar farm40under constructionupdated Feb 2026Jul 2023granted Oct 2024Feb 2026South Ayrshire6.1
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Air Traffic Control Centre, Fresson Avenuesolar farmsolar farm0.5approved, not builtupdated Nov 2024Jul 2024granted Nov 2024Nov 2024South Ayrshire3.1
Craig Tara Holiday Park, Dunure Roadrooftop solarrooftop solar0.7approved, not built may be out of dateupdated Jul 2023Jun 2023granted Jul 2023Jul 2023South Ayrshire6.5
Enterkine House, Annbanksolar farmsolar farm0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023South Ayrshire7.1

Distance from the average position of the KA8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3030040.6
Rooftop solar101000.7
Wind turbine110001
Battery storage40400745

MW in pipeline: pending, approved and under-construction capacity.

How South Ayrshire decides solar, wind and battery applications

ApplicationsSouth AyrshireUK
Decided applications (solar, wind, battery)2010,236
Refused12 (60%)19%
Solar refused0 of 612%
Onshore wind refused12 of 1345%
Battery storage refused0 of 116%
Median time from submission to decision41.7 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

All projects in South Ayrshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KA8, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.