Holmston Road (49.9 MW battery storage)

Holmston Road is a 49.9 MW battery storage project in South Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2025; the record was last updated on 5 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
under constructionstatus in REPD
5 August 2025record last updated
South Ayrshirecouncil area

Planning timeline

DateStage
17 March 2023Application submitted
30 June 2023Planning permission granted
1 July 2025Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
5 August 2025
Operator or applicant
Field Energy
Planning authority
South Ayrshire
Planning application reference
22/00505/PAN
Address (REPD)
Holmston Farm Holmston Road Ayr
Council area (by location)
South Ayrshire
Time to decision
15 weeks
Name in REPD
Holmston Road - Battery Storage Facility
REPD reference
11679

Who decides

ApplicationsSouth AyrshireUK
Decided applications (solar, wind, battery)2010,236
Refused12 (60%)19%
Solar refused0 of 612%
Onshore wind refused12 of 1345%
Battery storage refused0 of 116%
Median time from submission to decision41.7 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Braston New Energybattery storage500approved, not built1.6
Belston Battery Storagebattery storage150approved, not built2.0
Loch Fergus Farm Solar Farmsolar farm40under construction4.0
Loch Fergus Farmbattery storage45under construction4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4573, -4.5905).