Killoch Depot, Killoch Colliery (49.9 MW battery storage)

Killoch Depot, Killoch Colliery is a 49.9 MW battery storage project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 March 2023, not yet built; the record was last updated on 17 April 2023. REPD also records that the planning permission expired on 30 March 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtmay be out of datestatus in REPD
17 April 2023record last updated
East Ayrshirecouncil area

REPD also records that the planning permission expired on 30 March 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
28 September 2022Application submitted
30 March 2023Planning permission granted
30 March 2026Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
17 April 2023
Operator or applicant
Brockwell Energy Limited
Planning authority
East Ayrshire
Planning application reference
22/0405/PP
Address (REPD)
Killoch Depot Killoch Colliery Off A70 West Of Ochiltree Ochiltree
Council area (by location)
East Ayrshire
Time to decision
26 weeks
Name in REPD
Killoch Depot, Killoch Colliery - Battery Storage
REPD reference
12349

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Coylton Substation, Coyltonbattery storage50under construction1.9
Electricity Substation, Bardarrochbattery storage29.9approved, not built2.2
Polquhairn Wind Farmwind farm34.2application withdrawn5.9
Kyle Windfarmwind farm255refused9.2
Loch Fergus Farm Solar Farmsolar farm40under construction9.3
Loch Fergus Farmbattery storage45under construction9.3
Belston Battery Storagebattery storage150approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4559, -4.4028).