Energy Projects Near You

Electricity Substation, Bardarroch (29.9 MW battery storage)

Electricity Substation, Bardarroch is a 29.9 MW battery storage project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 March 2025, not yet built; the record was last updated on 6 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29.9 MWbattery storage
approved, not builtstatus in REPD
6 May 2025record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
28 November 2023Application submitted
4 March 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
29.9 MW
Status (REPD)
approved, not built
Record last updated
6 May 2025
Operator or applicant
Balance Power Projects Limited
Planning authority
East Ayrshire
Planning application reference
23/0604/PP
Address (REPD)
S/O Electricity Substation, A70 From B730 To U74 Bardarroch, Ochiltree, Cumnock
Council area (by location)
East Ayrshire
Time to decision
66 weeks
Name in REPD
Electricity Substation, Bardarroch - Battery Energy Storage
REPD reference
15569

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Coylton Substation, Coyltonbattery storage50under construction0.2
Killoch Depot, Killoch Collierybattery storage49.9approved, not built2.2
Polquhairn Wind Farmwind farm34.2application withdrawn4.9
Loch Fergus Farmbattery storage45under construction7.3
Loch Fergus Farm Solar Farmsolar farm40under construction7.3
Belston Battery Storagebattery storage150approved, not built8.1
Kyle Windfarmwind farm255refused8.6
Over Hill Wind Farmwind farm36approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4451, -4.4313).