Over Hill Wind Farm (36 MW)

Over Hill Wind Farm is a 36 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 July 2023, not yet built; the record was last updated on 16 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWwind farm
approved, not builtstatus in REPD
16 September 2020record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
16 September 2020Application submitted
30 September 2021Refused by the planning authority
10 December 2021Appeal lodged
7 July 2023Planning permission granted
7 July 2023Appeal allowed
7 July 2028Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
36 MW
Status (REPD)
approved, not built
Record last updated
16 September 2020
Operator or applicant
EnergieKontor (EKUK)
Planning authority
East Ayrshire
Planning application reference
20/0425/PP
Appeal reference
21/0020/REF
Turbines
10
Turbine height
180 m
Address (REPD)
Over Hill, New Cumnock, Cumnock, Strathclyde
Council area (by location)
East Ayrshire
Time to decision
146 weeks
REPD reference
10264

Earlier applications for this site

ApplicationMWSubmittedOutcome
Over Hill Wind Farm 17/0395/PP3326 May 2017replaced by a revised application

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kyle Windfarmwind farm255refused2.2
North Kyle Energy Projectwind farm206under construction2.5
Chalmerstonwind farm50application withdrawn3.1
Polquhairn Wind Farmwind farm34.2application withdrawn5.3
Burnhead Wind Farmwind farm18.4refused on appeal5.8
Greenburn Wind Parkwind farm67.2approved, not built5.8
Greenburn Wind Parkbattery storage10approved, not built5.8
Pencloe Wind Farmwind farm81under construction6.0
South Kyle Wind Farm 2wind farm92.4application submitted6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3723, -4.3418).