Chalmerston (50 MW wind farm)
Chalmerston is a 50 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 29 June 2005; the record was last updated on 29 June 2005.
50 MWwind farm
application withdrawnstatus in REPD
29 June 2005record last updated
East Ayrshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 16 April 2004 | Application submitted |
| 29 June 2005 | Application withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 50 MW
- Status (REPD)
- application withdrawn
- Record last updated
- 29 June 2005
- Operator or applicant
- Hargreaves Resources
- Planning authority
- East Ayrshire
- Planning application reference
- 04/0406/FL
- Address (REPD)
- Dalmellington , East Ayrshire
- Council area (by location)
- East Ayrshire
- REPD reference
- 3216
Who decides
| Applications | East Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 36 | 10,236 |
| Refused | 17 (47%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 17 of 25 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 95.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| North Kyle Energy Project | wind farm | 206 | under construction | 0.8 |
| Kyle Windfarm | wind farm | 255 | refused | 2.8 |
| Over Hill Wind Farm | wind farm | 36 | approved, not built | 3.1 |
| Burnhead Wind Farm | wind farm | 18.4 | refused on appeal | 3.3 |
| South Kyle Wind Farm 2 | wind farm | 92.4 | application submitted | 3.4 |
| Breezy Hill, North Kyle Forest Estate | battery storage | 40 | application submitted | 3.6 |
| Breezy Hill, North Kyle Forest Estate | wind farm | 100 | application submitted | 3.6 |
| Enoch Hill 2 Windfarm | wind farm | 10 | approved, not built | 5.2 |
| Enoch Hill, Dalmellington | battery storage | 11 | approved, not built | 5.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3497, -4.3712).