Enoch Hill 2 Windfarm (10 MW)

Enoch Hill 2 Windfarm is a 10 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 July 2025, not yet built; the record was last updated on 10 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
approved, not builtstatus in REPD
10 February 2026record last updated
East Ayrshirecouncil area

Planning timeline

DateStage
4 September 2023Application submitted
17 July 2025Planning permission granted
17 July 2028Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
10 February 2026
Operator or applicant
RWE Renewables Uk Limited
Planning authority
East Ayrshire
Planning application reference
23/0469/PP
Turbines
2
Turbine height
150 m
Address (REPD)
Enoch Hill Wind Farm, B741 From Armour Wynd To, U720 Dalricket Dalmellington, Ayr
Council area (by location)
East Ayrshire
Time to decision
97 weeks
Contracts for Difference
AR7a
REPD reference
7769

Recorded together with Enoch Hill, Dalmellington (11 MW battery storage, approved, not built).

Who decides

ApplicationsEast AyrshireUK
Decided applications (solar, wind, battery)3610,236
Refused17 (47%)19%
Solar refused0 of 612%
Onshore wind refused17 of 2545%
Battery storage refused0 of 516%
Median time from submission to decision95.7 weeks17.0 weeks
Appeals lodged / allowed11 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Breezy Hill, North Kyle Forest Estatebattery storage40application submitted2.2
Breezy Hill, North Kyle Forest Estatewind farm100application submitted2.2
Dersalloch Battery Storage Facilitybattery storage50approved, not built2.3
South Kyle Wind Farm 2wind farm92.4application submitted2.9
Burnhead Wind Farmwind farm18.4refused on appeal2.9
Knockkippen Wind, Solar & Battery Farmsolar farm20approved, not built3.0
Knockkippen Wind, Solar & Battery Farmwind farm60approved, not built3.0
Dersallochwind farm69operational3.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3248, -4.4416).