Enoch Hill 2 Windfarm (10 MW)
Enoch Hill 2 Windfarm is a 10 MW wind farm project in East Ayrshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 July 2025, not yet built; the record was last updated on 10 February 2026.
10 MWwind farm
approved, not builtstatus in REPD
10 February 2026record last updated
East Ayrshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 4 September 2023 | Application submitted |
| 17 July 2025 | Planning permission granted |
| 17 July 2028 | Permission due to expire (unless work starts) |
Project details
- Technology
- wind farm
- Capacity
- 10 MW
- Status (REPD)
- approved, not built
- Record last updated
- 10 February 2026
- Operator or applicant
- RWE Renewables Uk Limited
- Planning authority
- East Ayrshire
- Planning application reference
- 23/0469/PP
- Turbines
- 2
- Turbine height
- 150 m
- Address (REPD)
- Enoch Hill Wind Farm, B741 From Armour Wynd To, U720 Dalricket Dalmellington, Ayr
- Council area (by location)
- East Ayrshire
- Time to decision
- 97 weeks
- Contracts for Difference
- AR7a
- REPD reference
- 7769
Recorded together with Enoch Hill, Dalmellington (11 MW battery storage, approved, not built).
Who decides
| Applications | East Ayrshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 36 | 10,236 |
| Refused | 17 (47%) | 19% |
| Solar refused | 0 of 6 | 12% |
| Onshore wind refused | 17 of 25 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 95.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 11 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Breezy Hill, North Kyle Forest Estate | battery storage | 40 | application submitted | 2.2 |
| Breezy Hill, North Kyle Forest Estate | wind farm | 100 | application submitted | 2.2 |
| Dersalloch Battery Storage Facility | battery storage | 50 | approved, not built | 2.3 |
| South Kyle Wind Farm 2 | wind farm | 92.4 | application submitted | 2.9 |
| Burnhead Wind Farm | wind farm | 18.4 | refused on appeal | 2.9 |
| Knockkippen Wind, Solar & Battery Farm | solar farm | 20 | approved, not built | 3.0 |
| Knockkippen Wind, Solar & Battery Farm | wind farm | 60 | approved, not built | 3.0 |
| Dersalloch | wind farm | 69 | operational | 3.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.3248, -4.4416).